<br /> Contract Unit Current Quantity Amount
<br />No. Item Unit Quantity Price Quantity to Date to Date
<br /> PART 1 . SITE GRADING:
<br />1 MOBILIZATION LS 1 10000.00 0.25 0.75 $7,500.00
<br />2 TRAFFIC CONTROL LS 1 2250.00 0.25 0.75 $1,687.50
<br />3 SILT FENCE, REGULAR LF 3600 1.60 2659 $4,254.40
<br />4 CLEAR AND GRUB LS 1 16000.00 0.25 1 $16,000.00
<br />5 COMMON EXCAVATION (P) CY 66400 1.93 35000 $67,550.00
<br />6 GRANULAR BORROW (CV) CY 11000 10.90 6818 6818 $74,316.20
<br />7 SALVAGE AND RESPREAD TOPSOIL, 4" THICK LS 1 12950.00 0.5 1 $12,950.00
<br />8 HAUL EXCESS TOPSOIL OFFSITE CY 10000 1.10 10000 $11,000.00
<br />9 SHEEHY PROPERTY ACQUISITION DELAY - SEE SPECS LS 1 5000.00 1 $5,000.00
<br />10 EROSION CONTROL BLANKETS, CATEGORY 4 SY 2200 1.70 400 400 $680.00
<br />11 TEMPORARY ROCK CHECK, CLASS I-IV CY 75 95.00 7 $665.00
<br />12 GEOTEXTILE FABRIC FOR ROCK CHECK, TYPE IV SY 110 10.00 10 $100.00
<br />13 12" BIOROLL LF 150 6.50 $0.00
<br />14 24" STORM SEWER CULVERT LF 30 35.00 24 $840.00
<br /> TOTAL PART 1 - SITE GRADING: $202,543.10
<br /> PART 2 -SANITARY SEWER:
<br />15 CONNECT TO EXISTING SANITARY SEWER 8" PVC PIPE EA 1 2000.00 1 $2,000.00
<br />16 8" PVC SANITARY SEWER, SDR 35 LF 980 26.00 584 974 $25,324.00
<br />17 4' DIAMETER SANITARY MH, 8' DEEP EA 4 1850.00 2 4 $7,400.00
<br />18 4' DIAMETER.SANITARY MANHOLE OVERDEPTH LF 9 110.00 7.63 $839.30
<br />19 INSULATION, 4" THICK SF 650 2.00 $0.00
<br />20 CLOSED CIRCUIT TV INSPECTION LF 980 1.00 $0.00
<br />21 IMPROVED PIPE FOUNDATION, PER 6" INCREMENT LF 980 1.00 $0.00
<br /> TOTAL PART 2 - SANITARY SEWER: $35,563.30
<br /> PART 3. WATER MAIN:
<br />22 REMOVE WATER MAIN LF 90 20.00 160 $3,200.00
<br />23 SALVAGE HYDRANT EA 1 1000.00 1 $1,000.00
<br />24 JACK 12"WATERMAIN WITH CARRIER PIPE LF 55 390.00 57 $22,230.00
<br />25 CONNECT TO EXISTING 8" WATER MAIN EA 1 1000.00 1 $1,000.00
<br />26 12" X 12"WET TAP EA 1 3200.00 1 $3,200.00
<br />27 12" PVC WATER MAIN LF 1450 31.00 975 1425 $44,175.00
<br />28 8" PVCWATER MAIN LF 840 21.00 820 820 $17,220.00
<br />29 6" PVCWATER MAIN LF 60 18.00 50 58.5 $1,053.00
<br />30 12" GATE VALVE AND BOX EA 1 1600.00 1 1 $1,600.00
<br />31 8" GATE VALVE AND BOX EA 2 950.00 2 2 $1,900.00
<br />32 6" GATE VALVE AND BOX EA 4 750.00 4 4 $3,000.00
<br />33 HYDRANT WITH VALVE EA 4 2700.00 4 4 $10,800.00
<br />34 12" FITTING RESTRAINT EA 26 85.00 24 26 $2,210.00
<br />35 8" FITTING RESTRAINT EA 15 48.00 15 15 $720.00
<br />36 6" FITTING RESTRAINT EA 32 39.00 27 32 $1,248.00
<br />37 12" 22,5 DEGREE BEND EA 4 380.00 4 4 $1,520.00
<br />38 12" X 6" TEE EA 7 480.00 6 7 $3,360.00
<br />39 8" 90 DEGREE BEND EA 2 235.00 2 2 $470.00
<br />40 8" X 6" TEE EA 1 300.00 1 1 $300.00
<br />41 8" X 8" TEE EA 1 375.00 1 1 $375.00
<br />42 12" X 8" REDUCER EA 1 270.00 1 1 $270.00
<br />43 8" PLUG EA 1 100.00 1 $100.00
<br />44 IMPROVED PIPE FOUNDATION, PER 6" INCREMENT LF 2000 1.00 $0.00
<br /> TOTAL PART 3 - WATER MAIN: $120,951.00
<br /> PART 4 . SERVICES:
<br />45 6" PVC, SCH. 40 SERVICE PIPE LF 166 16.00 150 150 $2,400.00
<br />46 6" PVCWATER MAIN LF 120 20.00 110 110 $2,200.00
<br />47 6" GATE VALVE AND BOX EA 4 750.00 4 4 $3,000.00
<br />48 8" X 6" PVC WYE EA 4 100.00 4 4 $400.00
<br />49 6" PLUG EA 4 80.00 4 4 $320.00
<br /> TOTAL PART 4 - SERVICES: $8,320.00
<br /> PART 5 -STORM SEWER:
<br />50 42" RCP STORM SEWER LF 445 107.00 440 440 $47,080.00
<br />51 24" RCP STORM SEWER LF 230 37.00 226 226 $8,362.00
<br />52 18" RCP STORM SEWER LF 520 31.00 299 299 $9,269.00
<br />53 15" RCP STORM SEWER LF 1125 28.00 990 990 $27,720.00