<br /> Contract Unit Quantity Amount
<br />No. Item Unit Quantity Price to Date to Date
<br /> Part 1 - Sanitary Sewer - Centerville Road
<br />1 Mobilization LS 1 13500.00 0.9 $12,150.00
<br />2 Traffic control LS 1 2912.00 0.9 $2,620.80
<br />3 Shouldering aggregate TN 50 24.45 $0.00
<br />4 Clear and Grub Tree 2 500.00 2 $1,000.00
<br />5 Silt fence, regular LF 200 2.00 $0.00
<br />6 Remove and replace 36" CMP LS 1 1500.00 $1,500.00
<br />7 Salvage and replace gravel driveway TN 20 17.07 $0.00
<br />8 Connect to existing manhole EA 1 1500.00 1 $1,500.00
<br />9 12" PVC, SOR 35,8'- 10' deep LF 250 28.09 250 $7,022.50
<br />10 12" PVC, SOR 35, 10'. 12' deep LF 175 28.09 175 $4,915.75
<br />11 12" PVC, SOR 35,12'.14' deep LF 10 28.09 10 $280.90
<br />12 12" PVC, SOR 35,14'.16' deep LF 265 28.09 265 $7,443.85
<br />13 12" PVC, SOR 26, 16'. 18' deep LF 5 30.54 5 $152.70
<br />14 12" PVC, SOR 26, 18' - 20' deep LF 15 30.54 15 $458.10
<br />15 4' dia. sanitary manhole EA 1 1394.73 1 $1,394.73
<br />16 Manhole overdepth LF 3 99.97 3 $299.91
<br />17 Adjust MH frame and ring casting EA 1 150.00 1 $150.00
<br />18 Remove bituminous street SY 330 2.00 250 $500.00
<br />19 Patch bituminous street SY 330 15.92 175 $2,786.00
<br />20 Salvage and reinstall 12" CMP culvert LF 40 16.67 40 $666.80
<br />21 Improved pipe foundation LF 720 0.01 $0.00
<br />22 Fiber blanket on steep slopes SY 600 2.08 $0.00
<br />23 Seeding with topsoil and mulch AC 0.75 998.40 $0.00
<br /> Total Part 1 - Sanitary Sewer - Centerville Road $44,842.04
<br /> Part 2 - Water Main - Centerville Road
<br />24 Connect to existing 12" water main EA 1 750.00 1 $750.00
<br />25 12" PVC, C900 LF 1062 23.B6 1062 $25,339.32
<br />26 B" PVC, C900 LF 35 16.71 35 $584.B5
<br />27 6" PVC, C900 LF 50 14.24 50 $712.00
<br />2B B" gate valve and box EA 1 652.74 1 $652.74
<br />29 12" butterfly valve and box EA 3 B51.33 3 $2,553.99
<br />30 Hydrant with gate valve and box EA 3 1899.17 3 $5,697.51
<br />31 Valve rod extension EA 7 143.49 7 $1,004.43
<br />32 Fittings LB 3000 1.15 2500 $2,875.00
<br />33 Improved pipe foundation LF 1100 0.01 $0.00
<br />34 Sodding SY 700 2.55 700 $1,785.00
<br />35 12" pipe restraint EA 20 69.64 20 $1,392.80
<br />36 B" pipe restraint EA 4 39.B5 4 $159.40
<br />37 Seeding with topsoil and mulCh AC 0.25 1018.64 $0.00
<br /> Total Part 2 - Water Main - Centerville Road $43,507.04
<br /> Part 3 . Services. Centerville Road
<br />38 12" x 6" PVC wye EA 2 236.27 2 $472.54
<br />39 12" x 4" PVC wye EA 2 229.88 2 $459.76
<br />40 4" PVC, Schedule 40 service pipe u= 40 11.22 35 $392.70
<br />41 6" HOPE sewer service directional drill LF 156 42.02 150 $6,303.00
<br />42 4" PVC, Schedule 40 riser pipe LF 10 17.47 10 $174.70
<br />43 1" copper water service - LF 90 8.59 80 $687.20
<br />44 1" copper service directional drill LF 400 9.39 380 $3,568.20
<br />45 Reconnect water service EA 1 17B.76 1 $178.76
<br />46 Connect to existing sewer service EA 1 178.76 1 $178.76
<br />47 1" curb stop and box EA 6 132.51 6 $795.06
<br />48 1" corporation stop EA 7 143.16 7 $1,002.12
<br /> Total Part 3 - Services. Centerville Road $14,212.80
<br /> Part 4 . Sanitary Sewer - Hunters Crossing
<br />49 8" PVC, SOR 35,18'.20' deep. jacked LF 60 246.99 60 $14,819.40
<br />50 8" PVC, SOR 35,8'.10' deep LF 350 16.25 350 $5,687.50
<br />51 8" PVC, SOR 35, 10'.12' deep LF 900 18.37 900 $16,533.00
<br />52 B" PVC, SDR 35,12'.14' deep LF 300 18.37 300 $5,511.00
<br />53 8" PVC, SDR 35,14'.16' deep LF 500 20.14 493 $9,929.02
<br />54 4' diameter sanitary manhole EA 9 1362.87 10 $13,628.70
<br />55 Manhole overdepth LF 56 99.97 50 $4,998.50
<br />56 Improved pipe foundation LF 2000 0.01 $0.00
<br />Requesl #3