<br />Timeline for Pheasant Marsh Phase I ';2... ~ lots <br /> <br />A. Start of Development Grading Construction <br /> <br />May 2001 after road restrictions are lifted. <br /> <br />B. Start of Development Street and Utility Construction <br /> <br />July 2001 atter completion of grading. somewhat weather dependent. <br /> <br />C. Finish of Development construction ready Model Home starts <br /> <br />October 2001, somewhat weather dependent. <br /> <br />D. Completion of Model Homes <br /> <br />January-February 2002 Model Home Completion <br /> <br />E. Home Sales begin for Pheasant Marsh Phase <br /> <br />February 2002, coordinated wit h Parade 0 f Homes Spring Preview. <br /> <br />F. Start of New Home Construction - Building permits <br /> <br />March 2002 and beyond <br /> <br />G. First completion of Phase I Pheasant Marsh Homes - <br />Certificate of Occupancy <br /> <br />May - June 2002 <br /> <br />H. Opening of new Elementary School I Pheasant Marsh Phase J <br />Enrollments <br /> <br />September 2002 <br />