<br /> Contract Unit Current Quantity Amount
<br />No. Item Unit Quantity Price QuantIty to Date to Date
<br />98 PAVEMENT MESSAGE, lEFT TURN ARROW - EPOXY EA 5 125.00 5 $625.00
<br />99 TEMPORARY ROCK CONSTRUCTiON ENTRANCE EA 2 1000.00 2 $2,000.00
<br /> TOTAL PART 6 . STREETS: $367,478.69
<br /> PART 7 ' CSAH 54 RIGHT TURN lANE:
<br />100 TRAFFIC CONTROL lS I 1000.00 1 $1,000.00
<br />101 COMMON EXCAVATION (P) CY 230 15,00 230 $3,450.00
<br />102 SAWING BITUMINOUS IF 500 2.75 $0,00
<br />103 SU8GRADE PREPARATION. SY 750 0.75 750 $562,50
<br />104 AGGREGATE 8ASE, CLASS 5 TN 270 11.50 200 $2,300,00
<br />105 TYPE lV 3 NON WEARING COURSE MIXTURE (8) TN 95 58,00 61 151 $8,758.00
<br />106 TYPE MV3 NON-WEAR COURSE (C) TN 65 66,00 30.82 90.82 $5,994,12
<br />107 TYPE MV3 WEAR COURSE (e) TN 65 66.00 30,82 90,82 $5,994,12
<br />108 BITUMINOUS MATERIAL FOR TACK COAT GAL 80 2.60 50 $130,00
<br />109 4' SOliD LINE, WHITE EPOXY IF 720 0,50 695 $347.50
<br />110 PAVEMENT MESSAGE, RIGHT TURN ARROW - EPOXY EA 1 125.00 2 $250,00
<br />. 111 SEEDING AC 0,2 775,00 $0.00
<br /> TOTAL PART 7 - CSAH 54 RIGHT TURN LANE: $28,786,24
<br />CHANGE ORDER NO.1
<br />1 CREW TiME HR 35 725,00 35 $2,537,50
<br />2 8' DIP PLUG EA 1 73.49 1 $73.49
<br />3 CREW TIME HR 7 725.00 7 $5,075,00
<br />4 8' DIP 45 DEGREE 8END EA 4 279.88 4 $1,119.52
<br />5 8' PVC, (900 WATERMAIN IF 10 ,14.72 10 $147,20
<br />6 1.5" ROCK5TA81l1ZATION TN 15 1973 15 $295,95
<br />7 CREW TI ME HR 0,5 725,00 0,5 $362.50
<br /> TOTAL CHANGE ORDER NO.1: $9,611,16
<br />CHANGE ORDER NO.2
<br />1 8' DIP WATER MAIN, CLASS 52 IF 35 29.00 35 $1,015,00
<br />2 8' GATE VALVE AND 80X EA 1 950.00 1 $950,00
<br />3 CONNECT TO EXISTING 8' WATER MAIN EA 1 1000.00 1 S1.00000
<br />4 8" 90 DEGREE 8END EA 1 235.00 1 $235,00
<br />5 8" PLUG EA 1 100,00 1 $100.00
<br />6 8' FITTING RESTRAINT EA 4 48,00 5 $240.00
<br /> TOTAL CHANGE ORDER NO, 2: $3,540,00
<br />CHANGE ORDER NO.4
<br />1 MOBILIZATION lS 1 3000,00 1 $3,000,00
<br />2 2" RCP STORM SEWER IF 432 35,50 432 $15,336,00
<br />3 21" RCP FLARED END SECTION EA 1 1500.00 1 $1,500,00
<br />4 SALVAGE AND REINSTAll 6" PVC DRAINTllE IF 200 18.00 200 $3,600,00
<br />5 RIP RAP, CLASS III CY 15 100.00 15 $1,500,00
<br />6 RESTORE DRAINAGE SWAlE LS 1 2000.00 1 $2,000,00
<br /> TOTAl CHANGE ORDER NO, 4: $26,936.00
<br /> TOTAL PART 1 - SITE GRADING: $333,490,00
<br /> TOTAL PART 2 - SANITARY SEWER: $37,544,80
<br /> TOTAL PART 3 - WATER MAIN: $124,287,00
<br /> TOTAL PART 4 . SERVICES: $9,016,00
<br /> TOTAL PART 5 - STORM SEWER: $215,122.70
<br /> TOTAL PART 6 - STREETS: J367,478.69
<br /> TOTAl PART 7 - CSAH S4 RIGHT TURN LANE: $28,786 24
<br /> TOTAL CHANGE ORDER NO, 1: $9,611.16
<br /> TOTAl CHANGE ORDER NO.2: $3,54000
<br /> TOTAL CHANGE ORDER NO, 4: $26,936.00
<br /> TOTAL WORK COMPlETED TO DATE $1,155,812.58
<br /> 61605143REQ7.)l)s -13-