<br /> Contract Unit Quantity Amount
<br />No. Item Unit Quantity Price to Date to Date
<br /> Part 5 a Water Main a Hunters Crossing
<br />57 8" PVC, C900 " jacked LF 45 143.24 45 $6,445.80
<br />58 8" PVC, C900 LF 1330 14.05 1310 $18,405.50
<br />59 6" PVC, C900 LF 810 11.58 814 $9,426.12
<br />60 6" gate valve and box: EA 2 490.88 2 $981.72
<br />61 8" gate valve and box EA 4 652.74 4 $2,610.96
<br />62 Hydrant with gate valve and box EA 6 1899.17 6 $11,395.02
<br />63 Valve rod extension EA 12 98.49 12 $1,181.88
<br />64 Gate valve wrench, 8' long EA 1 39.08 $0.00
<br />65 Gate valve wrench, 3' long EA 2 23.11 $0.00
<br />66 Hydrant wrench EA 3 29.50 $0,00
<br />67 Fittings LB 3000 1.30 2500 $3,250.00
<br />68 Improved pipe foundation LF 1000 0.01 $0.00
<br />69 8" pipe restraint EA 24 39.82 24 $955.68
<br />70 6" pipe restraint EA 16 30.24 16 $483.84
<br />71 Insulation, 2" thick SY 20 17.46 $0.00
<br /> Total Part 5 - Water Main - Hunters Crossing $55,136.52
<br /> Part 6 - Services a Hunters Crossing
<br />72 8" x 4" PVC wye EA 37 76.63 37 $2,835.31
<br />73 4" PVC sewer service LF 1710 6.64 1829 $12,144.56
<br />74 4" PVC riser pipe LF 90 17.47 109 $1,904.23
<br />75 1" copper water service LF 1730 5.76 1934 $11,139.84
<br />76 1" curb stop and box EA 37 107.51 37 $3,977.87
<br />77 1" corporation stop EA 37 67.05 37 $2,480.85
<br />78 Curb box wrench EA 3 34.82 $0.00
<br /> Total Part 6 - Services - Hunters Crossing $34,482.66
<br /> Part 7 - Storm Sewer - Hunters Crossing
<br />79 12" HOPE LF 330 17.51 330 $5,778.30
<br />80 12" RCP, Class 5 LF 120 20.77 120 $2,492.40
<br />81 15" RCP, Class 5 LF 80 22.14 80 $1,771.20
<br />82 18" HOPE LF 215 22.91 215 $4,925.65
<br />83 18" RCP, Class 5 LF 210 24.16 238 $5,750.08
<br />84 Improved pipe foundation LF 500 0.01 $0.00
<br />85 Catch basin EA 4 942.19 4 $3,768.76
<br />86 Catch basin manhole EA 4 1371.39 4 $5,485.56 .
<br />87 Pond outlet structure EA 1 1898.07 1 $1,898.07
<br />88 12" RCP apron w/tra.sh guard EA 1 534.52 1 $534.52
<br />89 12" HDPE apron w/trash guard EA 1 254.43 1 $254.43
<br />90 18" RCP apron w/trash guard EA 1 649.81 1 $649.81
<br />91 18" HDPE apron w/trash guard EA 2 306.63 2 $613.26
<br />92 Rock riprap, Class 3 CY 25 65.00 40 $2,600.00
<br />93 Sodding SY 500 2.55 488 $1,244.40
<br /> Total Part 7 - Storm Sewer - Hunters Crossing $37,766.44
<br /> Part 8 a street ~ Hunters Crossing
<br />94 Mill bituminous strip LF 100 3.12 $0.00
<br />95 Subgrade preparation RO STA 24 125.00 24 $3,000.00
<br />96 Granular borrow (GV) CY 5000 9.71 5635 $54,715.85
<br />97 Aggregate base, Class 5 - streets TN 3300 9.30 3450 $32,085.00
<br />98 Aggregate base, Class 5 - trail TN 700 9.82 994 $9.761.08
<br />99 Type 31 B bituminous base course TN 700 27.51 822.28 $22,620.92
<br />100 Type 41 B bituminous wear course - streets TN 700 29.64 23.6 $699.50
<br />101 Type 41 A bituminous wear - trail TN 185 38.48 283 $10,889.84
<br />102 Bituminous material for tack coat GAL 400 1.30 100 $130.00
<br />103 Surmountable concrete curb and gutter LF 4400 6.66 4333 $28,857.78
<br />104 Barricade EA 2 234.00 2 $468.00
<br />105 4" drain tile LF 4260 3.42 4105 $14,039.10
<br />106 Geotextile fabric SY 9000 1.35 9000 $12,150.00
<br />107 Seeding with topsoil and mulch AC 1.5 998.40 $0.00
<br /> Total Part 8 - Street - Hunters Crossing $189,417.07