<br /> Unit Quantity Quantity
<br />No. Item Unit Quantity Price This Period To Date Amount
<br /> BASE BID B - PEDESTAL SPHEROID
<br /> CONSTRUCTION:
<br />6 500,000 GALLON STEEL FLUTED COLUMN
<br /> WATER TOWER- TOTAL BASE BID A LS 1 $837,195.00
<br /> Breakdown of Base Bid B
<br />6a Design Drawings LS 1 $25,000 100.0% $25,000.00
<br />6b Foundation LS 1 $210,000 100.0% $210,000.00
<br />6e Steel Fabricated to Site LS 1 $235,895 20.0% 100.0% $235,895.00
<br />6d Field Erection LS 1 $138,000 30.0% 50.0% $69.000.00
<br />6e Field Painting LS 1 $190,000 $0.00
<br />6f Field Electrioal LS 1 $30,000 $0.00
<br />6g Cathodic Protection LS 1 $8,300 $0.00
<br /> Total Breakdown $539,895.00
<br /> FOUNDATION PILlNG- BASE BID B. PEDESTAL
<br /> SPHEROID PILING:
<br />16 9.518" DIA. CAST -IN-PLACE CONCRETE TEST PILE EA 2 $1,600.00 2 $3,200.00
<br />17 9-518' DIA CAST.IN.PLACE CONCRETE PILING,
<br /> DRIVEN LF 2080 $17 .00 2061 $35,037.00
<br /> TOTAL FOUNDATiON PILING $38,237.00
<br /> SITE WORK:
<br />20 SALVAGE AND REINSTALL CHAIN LINK FENCE LF 24 $29.15 24 24 $699.60
<br />21 SALVAGE, STOCKPILE, AND RESPREAD TOPSOIL LS 1 $100.00 1 1 $100.00
<br />22 REMOVE WATER MAIN LF 114 $10.00 114 114 $1,140.00
<br />23 REMOVE STREET SWEEPING MATERIAL CY 220 $5.00 $0.00
<br />24 SILT FENCE, REGULAR LF 600 $3.00 588 588 $1,764.00
<br />25 6' HIGH CHAIN LINK FENCE LF 135 $18.45 $0.00
<br />26 20' WiDE DOUBLE SWING GATE EA 1 $1,030.00 $0.00
<br />27 TYPE 41 BITUMINOUS FOR DRIVEWAYS TN 40 $40.00 $0.00
<br />28 TYPE 31 BITUMINOUS BASE COURSE TN 50 $40.00 $0.00
<br />29 AGGREGATE BASE, CLASS 5, 100% CRUSHED TN 700 $20.00 $0.00
<br />30 GEOTEXTILE FABRIC, TYPE V SY 360 $2.00 $0.00
<br />31 CONNECT TO EXISTING WATER MAIN EA 2 $500.00 2 2 $1,000.00
<br />32 16' PVC WATER MAIN LF 270 $45.00 285 286 $12,870.00
<br />33 16' DIP WA TERMAIN, CLASS 52, INCL. POLY LF 115 $40.00 110 110 $4,400.00
<br />34 6' DIP WATER MAIN, CL. 52, INCL. POLY WRAP LF 10 $25.00 18.5 18.5 $462.50
<br />35 6" GATE VALVE AND BOX EA 1 $650.00 2 2 $1,300.00
<br />36 12' GATE VALVE AND BOX EA 1 $1,500.00 1 1 $1,500.00
<br />37 16' GATE VALVE AND BOX EA 1 $4,000.00 1 1 $4,000.00
<br />38 CAST IRON FITTINGS LB 2065 $2.00 3089 3089 $6,178.00
<br />39 INSTALL HYDRANT EA 1 $1,800.00 1 1 $1,800.00
<br />40 OVERFLOW MANHOlE EA 1 $2,50000 1 1 $2,500.00
<br />41 15" RCP STORM SEWER LF 120 $30.00 104 104 $3,120.00
<br />42 15' RCP FLARED END SECTION EA 1 $500.00 1 1 $600.00
<br />43 CLASS III RIPRAP, PLACED AT FLARED END
<br /> SECTION CY 5 $100.00 5 5 $500.00
<br />44 MNDOT SEED MIX 70A AC 0.2 $5,000.00 $0.00
<br />45 WOOD FIBER BLANKET SY 500 $5.00 $0.00
<br /> TOTAL SITE WORK $43,834.10
<br /> TOTAL BASE BID B $539,895.00
<br /> TOTAL FOUNDATION PILINGS $38,237.00
<br /> TOTAL SITE WORK $43,834.10
<br /> TOTAL WORK COMPLETED TO DATE $621,966.10
<br /> MATERIALS ON HAND:
<br /> None $0.00
<br /> TOTAL STORED MATERIALS $0.00