<br /> Contract Unit Current Quantity Amount
<br />No. . Item Unit Quantity Price Quantity to Date to Date
<br />62 IMPROVED PIPE FOUNDATION LF 1000 4.00 215 $860.00
<br /> Total PART 2 - WATER MAIN IMPROVEMENTS: $311 ,287.00
<br /> PART 3 - STORM SEWER IMPROVEMENTS:
<br />63 24" RCP, CLASS 3 LF 460 35.00 459 $16,065.00
<br />64 18" RCP, CLASS 5 LF 662 30.00 702 $21,060.00
<br />65 16" RCP, CLASS 5 LF 1875 26.00 1222 1327 $34,502.00
<br />66 12" RCP, CLASS 5 LF 860 24.00 689 847 $20,328.00
<br />67 12" HDPE LF 560 19.00 518 518 $9,842.00
<br />68 10" PVC, SDR 26 LF 10 25.00 $0.00
<br />69 8" PERFORATED PVC LF 140 20.00 $0.00
<br />70 24" RCP FES WITH TRASH GUARD EA 1 1400.00 1 $1,400.00
<br />71 15" RCP FES WITH TRASH GUARD EA 5 750.00 4 $3,000.00
<br />72 12" HDPE FES WITH TRASH GUARD EA 1 175.00 2 2 $350.00
<br />73 12" RCP FES WITH TRASH GUARD EA 1 575.00 1 1 $575.00
<br />74 V2B1 STRUCTURE LS 1 9000.00 1 $9,000.00
<br />75 4' DIA MANHOLE EA 14 1600.00 8 12 $19,200.00
<br />76 4' DIA CATCH BASIN MANHOLE EA 17 1600.00 8 14 $22,400.00
<br />77 2 X 3 CATCH BASIN EA 15 1200.00 12 17 $20,400.00
<br />78 BEEHIVE CATCH BASIN EA 1 1200.00 $0.00
<br />79 FRENCH DRAIN EA 1 2500.00 1 1 $2,500.00
<br />80 GEOTEXTILE FABRIC, TYPE 2 NON-WOVEN SY 900 2.00 900 900 $1,800.00
<br />81 GEOTEXTILE FABRIC, TYPE 1 SY 70 2.75 70 70 $192.50
<br />82 GEOTEXTILE FABRIC, TYPE 4 SY 55 2.75 55 55 $151.25
<br />83 IMPROVED PIPE FOUNDATION LF 500 4.00 $0.00
<br />84 CONNECT TO EXISTING PIPE OR MANHOLE EA 5 600.00 1 3 $1,800.00
<br />85 REMOVE PIPE LF 200 8.00 18 224 $1,792.00
<br />86 REMOVE CATCH BASIN EA 4 600.00 3 4 $2,400.00
<br />87 SODDING SY 900 2.10 $0.00
<br />88 CLASS 3 RIPRAP CY 60 100.00 20 $2,000.00
<br />89 DITCH EXCAVATION LF 200 15.00 75 $1,125.00
<br />90 RECONSTRUCT CATCH BASIN MANHOLE EA 2 1600.00 2 $3,200.00
<br />91 PEA ROCK CY 20 25.00 10 10 $250.00
<br />92 COARSE (1.5" - 3") AGGREGATE TN 1360 16.00 1373.39 1373.39 $21,974.24
<br />93 CLEARING AND GRUBBING - HERITAGE STREET LS 1 2500.00 1 $2,500.00
<br />94 COMPOST ROLLS LF 160 10.00 $0.00
<br />95 LANDSCAPE EDGING LF 340 10.00 254 254 $2,540.00
<br />96 ROCK CONSTRUCTION ENTRANCE EA 5 500.00 $0.00
<br />97 6" - 18" GLACIAL BOULDERS TN 32 125.00 16.3 34.3 $4,287.50
<br />98 VEGETATED GEOGRID AND CHANNEL EXCAVATION CY 70 50.00 50 50 $2,500.00
<br />99 TOPSOIL BORROW (LV) CY 100 10.00 162 162 $1,620.00
<br />100 HERITAGE INFILTRATION TRENCH EXCAVATION (P) CY 930 10.00 630 930 $9,300.00
<br />101 BRIAN DRIVE FILTRATION SYSTEM LS 1 9500.00 $0.00
<br /> Total PART 3 - STORM SEWER IMPROVEMENTS: $240,054.49
<br /> PART 4 - LAMOTTE PARK IMPROVEMENTS:
<br />102 TYPE LV 3 WEARING COURSE MIXTURE - PARKING LOT TN 500 36.00 $0.00
<br />103 TYPE LV 3 WEARING COURSE MIXTURE - SKATE
<br /> PADITRAIL TN 150 46.00 187.61 $8,625.46
<br />104 TYPE LV 3 NON-WEARING COURSE MIXTURE-
<br /> PARKING LOT TN 475 35.50 503.5 $17,874.25
<br />105 BITUMINOUS MATERIAL FOR TACK COAT GAL 300 1.25 $0.00
<br />106 B612 CONCRETE CURB AND GUTTER LF 1200 7.75 900 $6,975.00
<br />107 COMMON EXCAVATION - SKATE PADITRAIL CY 635 12.00 635 $7,620.00
<br />108 CLASS 5 AGGREGATE BASE TN 800 10.00 534.35 $5,343.50
<br />109 SELECT GRANULAR BORROW (CV) CY 360 12.00 360 $4,320.00
<br />110 4" SOLID LINE, WHITE PAINT LF 1500 1.00 $0.00
<br />111 PAVEMENT MESSAGE, HANDICAP, PAINT EA 4 350.00 $0.00
<br />112 ADJUST CLEANOUT EA 3 300.00 $0.00
<br />113 4' HIGH CHAIN LINK FENCE LF 380 11.00 $0.00
<br />114 SODDING, LAWN TYPE, INCL 4" TOPSOIL SY 1000 2.10 $0.00
<br />115 SEEDING AC 0.5 1300.00 $0.00
<br />116 4" PERFORATED PVC DRAIN TILE LF 100 2.00 100 $200.00
<br /> Total PART 4 - LAMOTTE PARK IMPROVEMENTS: $50,958.21
<br />
<br />61603133REQ4.xls
<br />
|