Laserfiche WebLink
<br /> Contract Unit Current Quantity Amount <br />No. Item Unit Quantity Price Quantity to Date to Date <br /> Part 1 - Sanitary Sewer <br />1 MOBILIZATION LS 1 34000.00 1 $34,000.00 <br />2 8" PVC SANITARY SEWER, SDR 35, 8'.10' DEEP LF 225 25.65 225 $5,771.25 <br />3' 8" PVC SANITARY SEWER, SDR 35,10'.12' DEEP LF 100 25.65 100 $2,565.00 <br />4 8" PVC SANITARY SEWER, SDR 35,12'.14' DEEP LF 705 25.65 705 $18.083.25 <br />5 8" PVC SANITARY SEWER, SDR 35,14'.16' DEEP LF 340 25.65 140 $3,591.00 <br />6 12" PVC SANITARY SEWER, SDR 35,10'.12' DEEP LF 1020 27.75 1020 $28,305.00 <br />7 12" PVC SANITARY SEWER, SDR 35,12'.14' DEEP LF 1022 27.75 1022 $28,360.50 <br />8 12" PVC SANITARY SEWER, SDR 35, 14'.16' DEEP LF 570 27.75 571 $15,845.25 <br />9 4" PVC, SCH. 40 RISER PIPE LF 50 19.00 57 $1,083.00 <br />10 8" PVC FORCEMAIN LF 110 24.25 110 $2,667.50 <br />11 8" X4" PVC WYE EA 23 75.00 14 $1,050.00 <br />12 12" X 4" PVC WYE EA 14 130.00 21 $2,730.00 <br />13 4' DIAMETER SANITARY MH, 8' DEEP EA 19 1900.00 19 $36,100.00 <br />14 4' DIAMETER SANITARY MANHOLE OVERDEPTH LF 76 145.00 76 $11,020.00 <br />15 CONSTRUCT MANHOLE OVER EXISTING PIPE EA 1 2100.00 1 $2,100.00 <br />.16 IMPROVED PIPE FOUNDATION LF 3982 1.90 2551 $4,846.90 <br />17 SEEDING AC 1 1300.00 $0.00 <br />18 CLOSED CIRCUIT TV INSPECTION LF 3982 0.60 3783 $2,269.80 <br />19 CLEARING AND GRUBBING LS 1 5000.00 1 $5,000.00 <br /> Total Part 1 . Sanitary Sewer $205,388.45 <br /> Part 1 - Sanitary Sewer. Bid Amount Total. $214,261.00 <br /> Part 2 - Water Main <br />20 12" PVC WATER MAIN LF 3220 23.00 3223 $74,129.00 <br />21 8" PVC WATER MAIN LF 160 23.00 160 $3,680.00 <br />22 6" PVC WATER MAIN LF 600 23.00 557 $12,811.00 <br />23 12" GATE VALVE AND BOX EA 5 1300.00 5 $6,500.00 <br />24 8" GATE VALVE AND BOX EA 3 760.00 3 $2.280.00 <br />25 6" GATE VALVE AND BOX EA 6 565.00 6 $3,390.00 <br />26 INSTALL HYDRANT EA 4 2000.00 4 $8,000.00 <br />27 CONNECT TO EXISTING WATER MAIN EA 1 600.00 1 $600.00 <br />28 DUCTILE IRON FITTINGS LB 10000 0.85 10330 $8,780.50 <br />29 IMPROVED PIPE FOUNDATION LF 2000 1.90 1290 $2,451.00 <br />30 REMOVE BITUMINOUS DRIVEWAY SY 20 2.80 $0.00 <br />31 SAWING BITUMINOUS PAVEMENT LF 20 5.00 $0.00 <br />32 3" TYPE 41A, BIT. DRIVEWAY PAVEMENT SY 20 28.65 $0.00 <br />33 SEEDING AC 0.4 1300.00 $0.00 <br />34 SALVAGE AND REINSTALL GRAVEL DRIVEWAY SY 830 4.00 830 $3,320.00 <br />35 SALVAGE AND REINSTALL 24" RCP LS 1 670.00 1 $670.00 <br />36 AGGREGATE BASE, CLASS 5 TN 150 12.00 285 $3,420.00 <br />37 12" PIPE RESTRAINT EA 48 115.00 48 $5,520.00 <br />38 8" PIPE RESTRAINT EA 14 100.00 14 $1,400.00 <br />39 6" PIPE RESTRAINT EA 28 100.00 28 $2,800.00 <br /> Total Part 2. Water Main $139,751.50 <br /> Part 2. Water Main. Bid Amount Total. $141,369.00 <br /> Part 3 . Services <br />40 1" CORPORATION STOP EA 22 125.00 22 $2,750.00 <br />41 1" CURB STOP AND BOX EA 22 135.00 22 $2,970.00 <br />42 1" TYPE "K" COPPER WATER SERVICE LF 900 18.00 986 $17,748.00 <br />43 4" PVC, SCH. 40 SERVICE PIPE LF 1000 20.00 1049 $20,980.00 <br /> Total Part 3 . Services $44,448.00 <br /> Part 3. Services. Bid Amount Total. $41.920.00 <br /> Part 4 - Stann Sewer <br />44 12" RCP STORM SEWER, CLASS 5 LF 260 28.50 126 $3,591.00 <br />45 15" RCP STORM SEWER, CLASS 5 LF 990 30.00 315 $9,450.00 <br />46 27" RCP STORM SEWER. CLASS 3 LF 197 46.65 197 $9,190.05 <br />47 30" HDPE STORM SEWER LF 134 35.00 134 $4,690.00 <br />48 18" HDPE STORM SEWER LF 129 20.65 116 $2,395.40 <br />49 15" HOPE STORM SEWER LF 143 17.00 127 $2,159.00 <br />50 12" HDPE STORM SEWER LF 249 16.00 255 $4,080.00 <br />51 4' DIAMETER STORM CBMH EA 6 1500.00 6 $9,000.00 <br />52 5' DIAMETER STORM CBMH EA 3 2400.00 3 $7,200.00 <br />53 SKIMMER STRUCTURE EA 1 1100.00 1 $1,100.00 <br />116001 "\7R.EQ7FINAL.rls <br />