<br /> Unit Quantity Quantity
<br />No. Item U nit Quantity Price This Period To Date Amount
<br /> BASE BID B. PEDESTAl SPHEROID
<br /> CONSTRUCTION:
<br />5 500,000 GALLON STEEL FLUTED COLUMN
<br /> WATER TOWER. TOTAL BASE BID A LS $837,195.00
<br /> Breakdown of Base Bid B
<br />5. Design Dra'v\'ings LS $25,000 100.0% $25.000.00
<br />5b Foundation LS $210,000 100.0% $210,000.00
<br />5e Steel Fabricated to Site LS $235,895 100.0% $235,895.00
<br />5d Field Erection LS $138,000 100.0% $138,000.00
<br />5_ Field Painting LS $190,000 30.3% 80.0% $152,000.00
<br />5f Field Electrical LS $30,000 $0.00
<br />59 Cathodic Protection LS $8,300 $0.00
<br /> T cia! Br_akdown $750,895.00
<br /> FOUNDATION PILING. BASE BID B. PEDESTAL
<br /> SPH EROID PILlN G:
<br />15 9.5/8" DIA. CAST.IN.PLACE CONCRETE TEST PILE EA 2 $1,500.00 2 $3,200.00
<br />17 9-5/8" DIA. CAST-IN-PLACE CONCRETE PILING.
<br /> DRIVEN LF 2080 $17.00 2051 $35,037.00
<br /> TOTAL FOUNDATION PILING $38,237.00
<br /> SITE WORK:
<br />20 SALVAGE AND REINSTALL CHAIN LINK FENCE LF 24 $29.15 24 $599.50
<br />21 SALVAGE, STOCKPILE, AND RESPREAD TOPSOIL LS 1 $100.00 1 $100.00
<br />22 REMOVE WATER MAIN LF 114 $10.00 114 $1,140.00
<br />23 REMOVE STREET SWEEPING MATERIAL CY 220 $5.00 $0.00
<br />24 SILT FENCE, REGULAR LF 500 $3.00 588 $1,764.00
<br />25 5' HIGH CHAIN LINK FENCE LF 135 $18.45 $0.00
<br />25 20' WIDE DOUBLE SWING GATE EA 1 $1,030.00 $0.00
<br />27 TYPE 41 BITUMINOUS FOR DRIVEWAYS TN 40 $40.00 $0.00
<br />28 TYPE 31 BITUMINOUS BASE COURSE TN 50 $40.00 $0.00
<br />29 AGGREGATE BASE, CLASS 5, 100% CRUSHED TN 700 $20.00 $0.00
<br />30 GEOTEXTILE FABRIC, TYPE V SY 350 $2.00 $0.00
<br />31 CONNECT TO EXISTING WATER MAIN EA 2 $500.00 2 $1,000.00
<br />32 15" PVC WATER MAIN LF 270 $45.00 285 $12,870.00
<br />33 15" DIP WATERMAIN, CLASS 52, INCL. POLY LF 115 $40.00 110 $4,400.00
<br />34 6" DIP WATER MAIN, CL. 52, INCL. POLY WRAP LF 10 $25.00 18.5 $452.50
<br />35 6" GATE VALVE AND BOX EA 1 $650.00 2 $1,300.00
<br />36 12" GATE VALVE AND BOX EA 1 $1,500.00 1 $1,500.00
<br />37 16" GATE VALVE AND BOX EA 1 $4,000.00 1 $4,000.00
<br />38 CAST IRON FITTINGS LB 2055 $2.00 3089 $5,178.00
<br />39 INSTALL HYDRANT EA 1 $1,800.00 1 $1,800.00
<br />40 OVERFLOW MANHOLE EA 1 $2,500.00 1 $2,500.00
<br />41 15" RCP STORM SEW ER LF 120 $30.00 104 $3,120.00
<br />42 15" RCP FLARED END SECTION EA 1 $500.00 1 $500.00
<br />43 CLASS III RIPRAP, PLACED AT FLARED END
<br /> SECTION CY 5 $100.00 5 $500.00
<br />44 MNDOT SEED MIX 70A AC 0.2 $5,000.00 $0.00
<br />45 WOOD FIBER BLANKET SY 500 $5.00 $0.00
<br /> TOTAL SITE WORK $43,834.10
<br /> CHANGE ORDERS:
<br /> CHANGE ORDER NO.1
<br />1 ELIMINATE TANK EXTERIOR ILLUMINATION LS -$7,500.00
<br />2 ELIMINATE TANK CONTAINMENT 30.3% 80.0% .$38,400.00
<br /> REQUIREMENTS LS .$48,000.00
<br /> TOTAL CHANGE ORDER NO.1 -$38,400.00
<br /> TOTAL CHANGE ORDERS -$38,400.00