Laserfiche WebLink
<br />City of Centervllfe <br />PeltIer Lake Or. Area Street & Utility Imp. <br /> <br />Pagel <br />8/11/09 <br /> <br />Claim #3 (Work Order No. 4222) <br />In summary, the claim is for additional time and materials needed to complete the sewer repair <br />at and adjacent to MH 210A due to the presence of a sanitary sewer forcemain which was shown <br />on the drawings as being on the opposite side of said manhole. The forcemain made excavation <br />and backfill of the sewer more difficult and time-consuming. <br /> <br />City records showed the existing forcemaln to be on the west side of the sanitary manhole to <br />which we were to reconnect with the re-laid sewer. However, upon excavation of the area, it <br />was discovered that the forcemain was actually on the east side of the manhole, putting it In the <br />way of the sewer installation. Working around this forcemaln represents a change In conditions <br />and justifies the extra costs requested by this claim. However, the connection made to the <br />sanitary sewer manhole at this location was not core-cut. Therefore, the cost of the core-cut and <br />rubber boot should be deducted from this claim. Based on the bid price for a connection to an <br />existing manhole, we have estimated the cost of the deduct to be $600. <br /> <br />Claim #4 (Work Order No. 4560) <br />In summary, the claim is for additionai time and materials needed to re-Iay storm sewer pipe <br />after encountering a connict with the depth of the existing sanitary sewer force main. <br /> <br />Again, because of the lack of proper records of the exact location and elevation of the forcemaln <br />in this area, a connict with the storm sewer grade arose. In onder avoid the connict, several <br />lengths of pipe had to be reinstalled. This unforeseen condition justifies this claim. <br /> <br />Claim #5 (Work Order No. 4802) <br />In summary, the claim is for additional time spent by your crew while waiting to retrieve different <br />sized pipe than called for by the plan. <br /> <br />As with any work, existing conditions affecting the contractor's progress need to be checked by <br />your crews prior to beginning work. Additionally, if work is interrupted to retrieve materials not <br />immediately available, we expect that your crews would be kept busy doing something else on <br />the project as long as there still remains significant work left on the project. Therefore, this claim <br />is denied. <br /> <br />The following is a summary of the Claims addressed herein. <br /> <br />Claim Number <br />Claim # 1 <br />Claim #2 <br />Claim #3 <br />Claim #4 <br />Claim #5 <br />Total <br /> <br />Claim Amount <br />$3,992.00 <br />$381.57 <br />$3,004.26 <br />$2,699.00 <br />$803.59 <br />$10,850.42 <br /> <br />ADDroved Amount <br />$3,992.00 <br />$381.57 <br />$2,404.26 <br />$2,699.00 <br />$0.00 <br />$9,476.83 <br /> <br />If both parties (contractor and owner) are agreeable to the terms of the Engineer's review of the <br />claims as detailed above, we will draft and process a formal change order to incorporate this <br />work into the contract. <br /> <br />1_ <br />