Laserfiche WebLink
SUMMARY OF COSTS <br /> PELTIER LAKE DRIVE WATERMAIN EXTENSION VS. CREEK CROSSING <br /> OPTION 1 - NORTH CREEK CROSSING <br /> Construction Estimate $30,200 <br /> Easements (165 x 20) 8.000 <br /> Total Estimate $38,200 <br /> OPTION 2 - SOUTH CREEK CROSSING <br /> Construction Estimate $28,000 <br /> Easements (70 x 20) 3,400 <br /> Total Estimate $31,400 jpu <br /> OPTION 3 - PELTIER LAKE DRIVE WATERMAIN EXTENSION 6`� ^�� <br /> \ <br /> \oi <br /> Watermain $ 87,000 ,off <br /> Street Restoration 70,000 `' <br /> Landscaping 12.000 `N <br /> Construction Estimate $169,000 <br /> Overhead (35%) 59.150 �4 ° qo <br /> Total Project Estimate $228,150 AD 4 () 0 <br /> l <br /> Credit from Developer $35,000 fi <br /> Assessments $51,120 �ti <br /> Hook -up Fees $39,000 <br /> City Cost $103,030 <br /> 260 /090 -0406.feb <br />