Laserfiche WebLink
• <br /> COST ESTIMATE <br /> LIFT STATION NO. 2 <br /> CITY OF CENTERVILLE <br /> BRA File No. 61698000 <br /> Item Description Unit Quantity Cost Total Cost <br /> No. <br /> 1 Submersible pumps — FLYGT CP3127 I2,000 512,000 <br /> 2 Lift station control panel (no telemetry) 10,000 S10,000 <br /> . 3 Hatch LS 1 800 $800 <br /> 4 Piping 6" DIP FT 32' 24 5765 <br /> 5 Fittings 6" 90° LB 110 6 53,960 <br /> 6 Gate valves (buried) EA 2 600 51,200 <br /> 7 Check valves EA 2 800 51,600 <br /> 8 Mechanical labor LS 1 6,000 56,000 <br /> 9 Electrical labor LS 1 2,500 S2,500 <br /> 10 Remove existing pumps ! controls LS 1 8,000 S8,000 <br /> 11 By -pass pumping LS 1 7,000 S7,000 <br /> 12 Remove existing top slab LS 1 500 5500 <br /> 13 6' — 0" DIA x 5' manhole ext. FT 5 600 S3,000 <br /> 14 Top slab EA 1 900 S900 <br /> 15 Common fill YD 50 8 5400 <br /> Total Construction Costs = S58,628 <br /> r <br /> ii <br />