1. 2013 Street and Utility Improvements (193801520). Rice Creek Watershed has approved the
infiltration rate on the rain gardens, but will not final out the permit until bare spots in the rain gardens
have been successfully seeded.
2. Centerville Road (CSAH 21) Reconstruction (193801639). Steady progress has been made on
the north portion of the project. Storm sewer work on the large 48-inch storm sewer is nearly complete
as well as our water and sewer modifications. Street work should begin shortly.
The county is processing a formal change order to add the concrete intersection removals to the
project.
3. 21st Ave., North of Main St. (193802667). City staff is working through some final issues on this
project.
4. 2015 Mill and Overlay Project (193803042). Work has begun with curb replacements, structure
adjustments and patching. Milling of the bituminous is on-going at the time of this report and should
be completed by the end of the week. Restoration work behind the curb replacements will take place
before wear course paving to avoid damage to the wear course.
5. Miscellaneous(193803123).
• We are working with city staff to address FEMA floodplain issues with implications on real estate
transactions.
• We are reviewing sewer and water services to the property in the NW quadrant of Main Street
and Centerville Road to accommodate a potential business.