Loading...
HomeMy WebLinkAbout2015-05-13 Handout @ Mtg. CITY OF CENTERVILLE el,Viff MONTHL Y ENGINEER'S REPORT UWdt'ud IZ7 For the May 13, 2015 City Council Meeting Italics=New information. Normal = No change from last report. 1. 2013 Street and Utility Improvements (193801520). Rice Creek Watershed has approved the infiltration rate on the rain gardens, but will not final out the permit until bare spots in the rain gardens have been successfully seeded. 2. Centerville Road (CSAH 21) Reconstruction (193801639). Steady progress has been made on the north portion of the project. Storm sewer work on the large 48-inch storm sewer is nearly complete as well as our water and sewer modifications. Street work should begin shortly. The county is processing a formal change order to add the concrete intersection removals to the project. 3. 21st Ave., North of Main St. (193802667). City staff is working through some final issues on this project. 4. 2015 Mill and Overlay Project (193803042). Work has begun with curb replacements, structure adjustments and patching. Milling of the bituminous is on-going at the time of this report and should be completed by the end of the week. Restoration work behind the curb replacements will take place before wear course paving to avoid damage to the wear course. 5. Miscellaneous(193803123). • We are working with city staff to address FEMA floodplain issues with implications on real estate transactions. • We are reviewing sewer and water services to the property in the NW quadrant of Main Street and Centerville Road to accommodate a potential business.