HomeMy WebLinkAbout1973-03-08 Minutes PLANNING & ZONING MEETING March 8, 1973
PRESBNT:
Robert Wille, Jr., Attorney Walter Prachar
Mel Dupre Tom Wilharber
Fran Burque John Peterson
Leon L'Allier Lu Marcello
Norman Livgard Bob LaMotte
Gordy Rehbein Jerry Parent
Jim Schilling Ken Salin
Elmer Murray
Meeting was called to order at 7:15 pm by Bob LaMotte, Chairman.
Parent - Schilling plat was topic of meeting.
1st question: Culvert or pipe from road toward Creek or
silting basin. (100' pipe) 18" - Rice Creek requires
rip rap at end before Creek.
2nd street - extension on north end?
Ditch from Till Road - 20' easement - upkeep after develop-
ment - who is easement issued to? reserved? sloped bank on
ditch - private ditch?
Black top of Mill Road when streets are blacktopped?
Village P &Z have entered all requested changes and are
turning it over to Village Council to be accepted after
updating - engineers, attorney, surveyor - Jim and Jerry
and village council to finalize -the P & Z done all it can
do as of this date.
Jerry Parent was at latest Rice Creek Watershed meeting.
The Watershed Engineer read the correspondence from the
Village and everything UMS recommended and concurred with
was agreeable with the watershed.
Jim Schilling had in his possession the deed for the streets
that drawn the ,
U are Ul aYVll 111 U11G plot pSO.L1.
Mr. Wille is to check the abstract on north and south
parcels which are owned separately by Schilling and Parent.
One suggestion was made on Lot 4, Block 2. It should have
a 95' frontage if house is built at an angle.
Village Engineer Gotwold is to make final inspection on
streets when they are in and make recommendations on ditches.
-2
Village Engineer had sent his recommendations on cost and
materials for streets and Parent - Schilling were to get
their own figures for comparison.
Bond needed: Cash Escrow deposit or performance bond.
Park land: 10% gross area land prior to subdivision which
would be figured as follows: 25 lots, cost $30,000 brings
it to $120 payable per lot.
Percolation tests are to be taken subject to building
inspector recommendations.
Ken Salin made a motion to submit the Parent - Schilling
plot plan to council for approval as far as P &Z are con-
cerned. Tom Wilharber seconded it, motion carried.
Ken Salin made a motion to adjourn meeting. gordy Rehbein
seconded it, motion carried.
Meeting adjourned at 9:15 pm.
Council had short meeting and were discussing Parent -
Schilling plot plan when Schilling and Parent came back
to meeting and wanted a change in park land fees. They
thought the interpretation of Ordinance 15, Section 6,
paragraph 12 was read in error at meeting and should be
corrected while council was in session. They thought
the park land value read 10% of land value prior to sub -
division and as such the amount per lot should be $50 instead
of $120 as quoted at P &Z meeting. Walt to make further
investigation of this by calling Joe LaCasse to get the
value, of land before Parent and Schilling bought it.