June 9, 2010
Dallas Larson
Administrator
City of Centerville
1880 Main Street
Centerville, MN 55038 -9794
Re: Downtown Storm Water Reclamation Project
City of Centerville
Bonestroo File No.: 000616 - 08167 -0
Dear Dallas:
Bonestroo
At your request, we have prepared the following scope and fee proposal for the design and
bidding of the Downtown Storm Water Reclamation Project.
BACKGROUND
In May of 2008, we were authorized, by the City Council, to perform some preliminary design
work along with other pre - project tasks. Since that time, we have explored a number of
alternatives for treating the storm water which will be generated as part of the downtown
redevelopment. We have also assisted the City in obtaining several grants to help pay for these
improvements.
The ultimate project will consist of a network of storm sewer inlets and collection pipes feeding a
large diameter storm sewer pipe extending from the Downtown area to an existing ditch running
westward along the south edge of Laurie LaMotte Memorial Park. The schematic route of this
pipe is shown on the attached Figure 5. We will then utilize the existing pond in the Rice Creek
Chain of Lakes Regional Park Reserve as a reservoir for storm water to be used for irrigation of
the LaMotte balifields. The pond would hold enough water to provide the 16 acre site with one
inch of water per week for approximately three weeks without rain. A back -up system would be
provided to add water to the pond during extended drought periods. This system could be either
a small well or hydrant lead from the existing water system. The irrigation system will consist of
a pumping facility near the pond and a forcemain leading back to the ballfield area where it will
feed a network of irrigation lines.
Due to the pace of redevelopment in the downtown area, the decision was made to scale back
the 2010 project to just the irrigation system and pond modifications. Having met with the Rice
Creek Watershed District, the Board of Water and Soil Resources and Anoka County Parks
officials to gain their consensus on the revised project scope, we are now ready to move forward
with design and construction of the project should the City Council choose to do so.
City of Centerville
Downtown Strom Water Reclamation
� *0161a *$YATi fel 1
PRELIMINARY SURVEY
Under previous authorizations, we have completed some preliminary topographic surveys.
However, at the time, we were not certain of the final route of the pipe or placement of the
pond. Therefore, we will need to supplement this information with additional topographic
surveys of the ditch along the south side of LaMotte Park, Pond outlet, pump works site,
forcemain route and ballfields.
Page 2
6/9/10
Our work under this phase will include: Calling in a Gopher State One -Call Design Locate Ticket,
Topographic Survey work, locating existing property corners and measurements of existing utility
structures in the area.
PERMITTING AND AGENCY COORDINATION
Permits for this project will be required by:
Rice Creek Watershed District (RCWD) — Much of the up -front work of this permit process has
already been completed. From here on out, we will simply need to submit the formal application,
provide our calculations, drawings, and other documents for their review. Subsequently, we will
need to respond to their comments and resubmit, if necessary. The permitting process can
involve a few iterations, but we have been proactive in involving the district early in the design of
this project should reduce the time required to obtain a permit.
Anoka County — We do not anticipate the need for a permit from the county since we now have a
joint powers agreement governing the use of the pond. We will need to stay in communication
with Anoka County Parks as we work through the design, especially as it relates to site selection
for the pump works, trail modifications and other issues that will affect their park.
St. Paul Regional Water Services — Our forcemain and perhaps some ditch /culvert work may be
on land which is either owned by or has easement granted to the St. Paul Regional Water
Services. Their staff will review our plans and construction in these areas will require a permit
from the agency. We will work through the review process, addressing their comments and
submitting revisions, as necessary. We will also complete the initial application for the
construction permit. Final permit submittal, including any escrow /fee requirements will be made
by the contractor.
Minnesota Pollution Control Administration (MPCA) — A National Pollution Discharge Elimination
System (NPDES) permit for storm water discharge associated with general construction activity
will be required. We will complete the initial application for the construction permit. Final permit
submittal, including any escrow /fee requirements will be made by the contractor.
Lino Lakes — The ditch feeding the pond runs along the border between the Anoka County
regional park and a residential development which is part of the City of Lino Lakes. We do not
anticipate the need for a permit, but will need to coordinate with Lino Lakes City Staff and their
residents.
City of Centerville
Downtown Strom WaterRedamation
Page 3
6/9/10
Centerville Parks and Recreation Committee — Significant coordination with the Parks Committee
will be required to work out issues related to the irrigation system location and functionality. For
the purposes of this scope of work, we anticipate attending two (2) parks committee meetings.
ASSISTANCE WITH FUNDING APPLICTAIONS
The City has received funding for this project from the RCWD and the BWSR — Clean Water
Legacy Act. Both will require submittal of documentation, etc. to collect their funds. For the
purposes of this proposal, our scope will include only those activities needed prior to project
award. On -going reporting required during construction will be covered in a separate proposal at
the appropriate time.
City staff is applying for additional funding from several other sources. We will assist them by
providing technical information and documents required for these applications as requested. This
work would be done at our normal hourly rates and would be considered outside the scope of
this proposal since we do not know the specific requirements of these grants at this time.
ASSISTANCE WITH EASEMENTS
An easement along the alignment of the forcemain pipe may be necessary. The need for any
easements will be identified as we work through the design. We will provide easement
descriptions and sketches as necessary. This scope assumes the need for only one easement.
DESIGN & BIDDING
To this point we have done some preliminary storm water modeling of the pond and ditch. More
detailed modeling of the ditch should be completed once topographic survey information is
available. Additionally, the restriction of the existing culvert under the bike path will need to be
evaluated and modifications to the pond(s) will be designed. This work will be completed by our
specialized Water Resources Engineers, working in conjunction with our Civil Engineering staff.
Along with hydraulic concerns, there will be significant concerns regarding erosion potential. Our
specialized staff of erosion control experts will be involved to deal with those issues.
Our Civil engineering staff will design the route forcemain pipes. For the purposes of this
proposal, it is assumed that the route of the pipes will generally follow those shown on the
attached figure. Significant deviations from this route will be beyond the scope of this proposal.
We have spoken with industry representatives regarding the best approach to the design of the
pumpworks and irrigation system. It is the consensus of these folks and our conclusion that the
entire system should be designed and specified as part of the bidding documents. We will utilize
our expertise in designing large pumping stations and forcemains and will employ the services of
a specialized irrigation designer with whom we have worked in the past on similar projects.
The alternative to this approach is to have the contractor submit the design of these facilities as
part of the project, much like he would submit a set of shop drawings. Our staff would write
what is known as a "Performance Spec ". This document would tell the contractor the basic
requirements of the system, such as the pumping capacity, control capabilities, minimum quality
and performance requirements, power supply location, and other such pertinent information.
This approach can work in many cases and is a viable choice, given the right project. The
difficulty is writing a tight enough specification which does not allow cheap designs which meet
City ofCentemIlle
Downtown Strom water Redamation
Page 4
6/9110
the specification, but do not satisfy the intent of the project. If you bid the design of the system,
you will get the cheapest system possible, under the rules set in the specs. This will usually
exclude the best contractors who are not willing to compromise their reputation by providing a
cheap design.
If the City is not comfortable with our approach of writing a full specification, we can certainly
modify our scope of services to provide a performance spec and allow the contractor to design
the system.
As has been our practice, we will coordinate administration of the public bidding process,
including submitting advertisements for bid to the local paper and trade publication, responding
to bidder questions, issuing addenda and assisting the City with the receipt and tabulation of
bids. The scope of services outlined in this proposal ends with the award of the contract.
Services beyond that point will be presented in a separate, future proposal.
FEES
Item
Previous Current Total
Authorization Authorization
Preliminary, Pre - Project Work
$47,300
$47,300
Preliminary Survey
$4,280
$4,280
Permitting and Agency Coord.
$9,150
$9,150
Assistance w /Funding Apps.
$500
$500
Assistance w /Easements
$1,440
$1,440
Design & Bidding
$28,700
$28,700
Irrigation Designer
$7,500
$7,500
Total!
$47,300 $51,570
$98,870
Work will be billed on an hourly basis at our normal rates. For Preliminary Survey and
Design /Bidding phases, we will consider the figures above to be not -to- exceed limits. For the
Permitting, Funding and Easement phases, we request that these figures be viewed as estimates
based on the best information available at this time. The requirements for these phases can
often be fluid as the project takes shape and the effort required to complete the work can vary.
We will be present at the next City Council meeting to discuss this proposal and the project in
general. If the City Council wishes to move forward with the design and bidding of the project, it
would then be appropriate for them to authorize the completion of plans and specifications.
Sincerely,
BONESTR00
Mark Statz
City Engineer
651- 604 -4709
Attachments — Figure 5, Cost Estimate cc: Paul Palzer