Laserfiche WebLink
Page 2 <br /> Steven Sarkozy <br /> November 5, 1993 <br /> Apr. 14 Open bids <br /> Apr. 25 Award contract <br /> May 16 Start construction <br /> Sept. 16, 1994 Finish construction <br /> As you can see, the schedule allows limited time for council <br /> review and neighborhood committee discussions of available <br /> alternatives. This process must be completed by January 1, 1994 , <br /> to keep the project schedule on track. <br /> Please review this information and give me your thoughts. If you <br /> have any specific questions, let me know. <br /> cc; Gary Ehret, BRW <br />