it-Ol <br />481 <br />Mr. Schwartz noted that there were many variables, with undergrounding needing <br />482 <br />to be undertaken approximately one (1) year before the actual construction project <br />483 <br />to avoid potential conflicts with utility and road contractors; and challenges in <br />484 <br />having a defined right -of -way planned if expansion is part of the project, as well <br />485 <br />as whether there was the need for the county or city to purchase additional rights - <br />486 <br />of -way and cost prohibitions and unknowns in pre - planning under those <br />487 <br />circumstances. <br />Page 11 of 15 <br />