SECTION 3 — PROJECT SCHEDULE <br />A complete project schedule identifying maior activities and actions/decisions required from the client <br />*See Note Below <br />No Activity / Task Duration Start Date End Date <br />1 Notice to Proceed <br />2 Long Lead Items <br />3 Major Construction Activity <br />4 Major Construction Activity <br />5 Client Decision <br />6 Major Construction Activity <br />7 Major Construction Activity <br />8 Major Construction Activity <br />9 Major Construction Activity <br />10 Major Construction Activity <br />11 Client Decision <br />12 Substantial Completion <br />13 Final Payment <br />Contractor tasks are in "black'; Client tasks are in "blue'; Risky activities are in "red" <br />*Schedule to be coordinated with all proposal packages and will accommodate City of Roseville <br />Parks & Recreation program schedule provided in RFP. <br />*Detailed project schedule to be provided & approved by City prior to start date. <br />� <br />