Laserfiche WebLink
City of Roseville Arboretum <br />Restroom Facility Cost Estimate <br />11/12/08 <br />Building Construction costs: <br />726-882 s.f. ($200/s.f.) 150,000-175,000 <br />A/E costs @ 10% 20,000  25,000 <br />Site Work: 10,000  15,000 <br />Sanitary Sewer $127 LF (200) 25,400  25,400 <br />1€ copper water service $73 LF (200)14,600  14,600 <br />Contingency: 20,000  25,000 <br />Total: $240,000  279,000 <br />Phase 2 <br />Phase 2 Building Construction Costs (2008 prices) <br />726-882 s.f. 150,000-175,000 <br />A/E costs @ 10% 20,000  25,000 <br />Site Work: 10,000  15,000 <br />Contingency: 10,000  15,000 <br />Total: $190,000  230,000 <br />Grand Total $430,000  509,000 <br /> <br />