CITY OF ROSEVILLE <br />PARKS AND RECREATION RENEWAL PROGRAM <br />PROJECT PROGRESS REPORT <br />January 29, 2015 <br />PROJECT NAMESTART STATUSCOMMENTS <br />DATE <br />A.BUILDING <br />REPLACEMENT/SITE <br />Lexington Park 5/201496% complete Open House completed- <br />Punch list items <br />remainingand spring site <br />work <br />Sandcastle Park 6/201496% complete Open House completed- <br />Punch list items <br />remainingand spring site <br />work <br />Villa Park6/201595% complete Open House completed <br />January 28, 2015–punch <br />list items and spring site <br />work <br />Autumn Grove Park9/201475% complete,Open House Plannedfor <br />Framing begunfirst quarter 2015 <br />Oasis Park 9/201460% complete Open House Plannedfor <br />first quarter 2015 <br />Rosebrook Park 9/201450% complete Open House Plannedfor <br />first quarter 2015 <br />B.SHELTER REMODEL <br />CP FOR Parks–DALE STREET9/201495% completeFall completion planned <br />CP Foundation -WEST9/2014100% completeFall completion planned <br />CP Ballfields 9/201450% complete Fall completion planned <br />SKATING CENTER <br />C. <br />REPAIRS <br />Painting of Exterior 8/2014100 % complete <br />Replace exterior doors on Arena 100% complete <br />Block Work 2015 project <br />Vestibule Improvements 2015 project <br />D.HANC <br />Exterior Work 6/201495% complete <br />Interior Work 11/201480% complete2/2015 completion <br />Boardwalk 11/201480% built-to Spring 2015completion– <br />move on to site currently fabricating <br />for install <br />E.BRIDGE REPLACEMENT <br />Villa Park 7/20145% completeSpring2015 install <br />completion expected – <br />1 <br /> <br />