CITY OF ROSEVILLE <br />PARKS AND RECREATION RENEWAL PROGRAM <br />PROJECT PROGRESS REPORT <br />April 2, 2015 <br />PROJECT NAME START STATUS COMMENTS <br />DATE <br /> <br />A.BUILDING <br />REPLACEMENT/SITE <br />Lexington Park 5/2014 96% complete Open House completed- <br />Punch list items <br />remaining and spring site <br />work <br />Sandcastle Park 6/2014 96% complete Open House completed- <br />Punch list items <br />remaining and spring site <br />work <br />Villa Park 6/2015 95% complete Open House completed <br />January 28, 2015 –punch <br />list items and spring site <br />work <br />Autumn Grove Park 9/ 2014 96% complete, Open House completed <br />March 25 <br />Oasis Park 9/ 2014 70% complete Open House scheduled <br />for April 23, 2015 <br />Rosebrook Park 9/ 2014 70% complete Open House scheduled <br />for April 22, 2015 <br /> <br />B.SHELTER REMODEL <br />CP FOR Parks – DALE STREET 9/2014 95% complete Fall completion planned <br />CP Foundation - WEST 9/2014 100% complete Fall completion planned <br />CP Ballfields 9/2014 50% complete Fall completion planned <br /> <br /> <br />C. <br />SKATING CENTER <br /> <br />REPAIRS <br />Painting of Exterior 8/2014 100 % complete <br />Replace exterior doors on Arena 100% complete <br />Block Work 2015 project <br />Vestibule Improvements 2015 project <br /> <br /> <br />D.HANC <br />Exterior Work 6/2014 95% complete Punch list items only <br />Interior Work 11/2014 99% complete Open House completed <br />March 26, 2015 <br />Boardwalk 11/2014 95% complete Installation complete – <br />and installed now adjusting <br /> <br />E.BRIDGE REPLACEMENT <br />Villa Park 7/2014 80% complete Install scheduled in April, <br />Bridges built 2015 <br />1 <br /> <br />