Laserfiche WebLink
TABLE 2 <br />CT/RF WORK PLAN <br />Ex2ected <br />Bench and Pilot Study Report complete <br />8/15/85 <br />RCRA-Part A and B submitted <br />9/15/85 <br />In -plant modification specs mailed <br />10/1/85 <br />DEED IDB application submitted <br />10/1/85 <br />Purchase Roseville Site, initiate <br />11/15/85 <br />preconstructiott clearing and dr,-inage <br />Complete final engineering design <br />2/86 <br />Obtain IDB revenues <br />2/86 <br />Obtain PCA RCRA-Part B permit <br />3/86 <br />Initiate site construction and equipment orders <br />3/86 <br />Customer equipment purchase orders made <br />5/86 <br />Customer equipment ;nstallad and operational <br />10/86 <br />CT/RP complete, waste shipment; Accepted <br />12/86 <br />CT/RP fully operational <br />1/87 <br />