.y <br />Page 4 <br />MILESTONES AND TARGET DATES <br />PROJECT WORKPLAIV, — <br />The following timeline with specific da .es is proposed: <br />1/17/86 <br />submit PCA response to t .;RA Part-B Permit appli- <br />cation Completeness Review Deficiency List <br />3/31/86 - complete preliminary engineering work plan <br />4/15/86 - submit loan application to DEED and WMB <br />- initiate modifications to RCRA Part-B Permit <br />.1pplication if redesign is cost-effective based <br />on preliminary engineering results <br />5/15/86 - purchase site in Roseville <br />7/1/86 - resubmit RCRA Part-B Permit application modifica- <br />tions to PCA <br />- initiate final design engineering work <br />- in -plant modification plans of participating <br />companies submitted to Commission <br />10/1/86 - initiate site clearing and foundation excavation <br />11/3/86 - receive RCRA Part-B Permit <br />9/1/87 - facility complete and ready to accept waste <br />shipments <br />