<br />130 project is $60,800,000 and the LPCDS is estimated at $14,500,000. The soft cost for <br />131 Concept C for the MOC portion was $12,920,702 and for the LPCDS was $3,348,394. Soft <br />132 costs cover architect design fees, construction management fees, permits, inspections, <br />133 utility connections, preconstruction surveys/studies, testing, bidding, legal and finance <br />134 expenses, City purchase orders and FF&E expenses. <br />135 <br />136 Below is a table with the updated project budget including a breakdown of soft costs. Two <br />137 of the major soft cost components is the architect design fees and the Construction <br />138 Manager at Risk (CmaR) fees. The architect’s costs for the Civic Campus Master Project, <br />139 LHB, is included in the table below: <br />140 <br />141 <br />142 <br />143 Maintenance Operation Center costs can be funded using funding from the 0.5% local <br />144 sales tax approved last November totaling $64,200,000. <br />145 <br />146 Funding for the LPCDS costs has not been fully identified. <br />147 <br />148 Staff Recommendations <br />149 Staff recommends the Council approve the selection of Kraus-Anderson for Construction <br />150 Manager at Risk services related to the Civic Campus Project. <br />151 <br />152 Requested Council Action <br />153 Approve the selection of Kraus-Anderson for Construction Manager at Risk services related <br />154 to the Civic Campus Project. <br />155 <br />156 <br />Jesse Freihammer, Public Works Director <br />Prepared by: <br />1. – CMaR Services <br />Attachments: <br />2. – CMaR Services <br />3.Kraus-Anderson - RFQ Response <br />4.KA - Proposal <br />5.RJM RFQ <br />6.RJM - Proposal <br />7. Project Estimate – July 2022 from Civic Campus Update Report <br />8.Bench Handout 1 - Kraus-Anderson_Redacted <br />157 <br />Page 5 of 5 <br />Qbhf!292!pg!:15 <br /> <br />