Laserfiche WebLink
ARTICLE7 COSTOFTHEWORKFORCONSTRUCTIONPHASE <br />§7.1 CoststoBeReimbursed <br />§7.1.1 The term Cost of the Work shall mean costs necessarily incurred by the Construction Manager in the proper <br />performance of the Work. The Cost of the Work shall include only the items set forth in Sections 7.1 through 7.7. <br />§7.1.2 Where, pursuant to the Contract Documents, any cost is subject to the Owner’s prior approval, the Construction <br />Manager shall obtain such approval in writing prior to incurring the cost.The Owner’s execution of the Guaranteed Maximum <br />Price Amendment shall constitute the Owner’s approval of all costs identified within the Guaranteed Maximum Price. <br />§7.1.3 Costs shall be at rates not higher than the standard rates paid at the place of the Project, except with prior approval of <br />the Owner. <br />§7.2 LaborCosts <br />§7.2.1 Wages or salaries of construction workers directly employed by the Construction Manager to perform the construction <br />of the Work at the site or, with the Owner’s prior approval, at off-site workshopsat the rates set forth in Exhibit C. <br />§7.2.2 Wages or salaries of the Construction Manager’s supervisory and administrative personnel when stationed at the site <br />and performing Workat the rates set forth in Exhibit C. <br />§7.2.2.1 Wages or salaries of the Construction Manager’s supervisory and administrative personnel when performing Work <br />and stationed at a location other than the site, but only for that portion of time required for the Workat the rates set forth in <br />Exhibit C. <br />§7.2.3 Wages and salaries of the Construction Manager’s supervisory or administrative personnel engaged at factories, <br />workshops or while traveling, in expediting the production or transportation of materials or equipment required for the Work, <br />but only for that portion of their time required for the Workat the rates set forth in Exhibit C. <br />§7.2.4 Costs paid or incurred by the Construction Manager,as required by law or collective bargaining agreements, for taxes, <br />insurance, contributions, assessments and benefits and, for personnel not covered by collective bargaining agreements, <br />customary benefits such as sick leave, medical and health benefits, holidays, vacations and pensions, provided such costs are <br />based on wages and salaries included in the Cost of the Work under Sections 7.2.1 through 7.2.3.Such costs for taxes, <br />insurance, contributions, and assessments (excluding benefits) shall be forty-six percent (46%) of gross payroll. Gross payroll <br />consists of wages and benefits. <br />§7.2.5 If agreed rates for labor costs, in lieu of actual costs, are provided in this Agreement, the rates shall remain unchanged <br />throughout the duration of this Agreement, unless the parties execute a Modification. <br />§7.3 SubcontractCosts <br />Payments made by the Construction Manager to Subcontractors in accordance with the requirements of the subcontracts and <br />this Agreement. <br />§7.4 CostsofMaterialsandEquipmentIncorporatedintheCompletedConstruction <br />§7.4.1 Costs, including transportation and storage at the site, of materials and equipment incorporated, or to be incorporated, <br />in the completed construction. <br />§7.4.2 Costs of materials described in the preceding Section 7.4.1 in excess of those actually installed to allow for reasonable <br />waste and spoilage. Unused excess materials, if any, shall become the Owner’s property at the completion of the Work or, at <br />the Owner’s option, shall be sold by the Construction Manager. Any amounts realized from such sales shall be credited to the <br />Owner as a deduction from the Cost of the Work. <br />§7.5 CostsofOtherMaterialsandEquipment,TemporaryFacilitiesandRelatedItems <br />§7.5.1 Costs of transportation, storage, installation, dismantling, maintenance, and removal of materials, supplies, temporary <br />facilities, machinery, equipment and hand tools not customarily owned by construction workers that are provided by the <br />Construction Manager at the site and fully consumed in the performance of the Work. Costs of materials, supplies, temporary <br />AIA Document A133 –2019. Copyright © 1991, 2003, 2009, and 2019. All rights reserved. “The American Institute of Architects,” “American Institute of <br />Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects.This draft was produced at 13:53:13 CDT <br />13 <br />on 08/18/2025 under Subscription No.20250116558 which expires on , is not for resale, is licensed for one-time use only, and may only be used in accordance <br />® <br />with the AIA Contract DocumentsTerms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com. <br />User Notes: (640e2aedf442e4498d096805) <br />Qbhf!255!pg!74: <br /> <br />