Roseville PWET Commission Meeting Minutes <br />Page 2 -November 24, 2009 <br />City Engineer Bloom and Public Works Director Schwartz detailed work <br />completed on the project to-date and being finalized before winter on the Twin <br />Lakes Infrastructure Project, detailing work completed to-date before winter, and <br />that work deferred until the 2010 construction season, with the majority of the <br />project completed by the December 14, 2009 deadline and scheduled grand <br />opening for the Park and Ride Facility by Metropolitan Transit. Mr. Schwartz <br />discussed Phase II of the project, with receipt by the City of a $1 million <br />Department of Employment and Economic Development (DEED) for Twin Lakes <br />Parkway from the existing round about to the next round about and signal at Prior <br />and County Road C; with preliminary costs going before the City Council in <br />December for a potential 2010 project, requiring a city match component. Mr. <br />Schwartz advised that, while approximately $ l ,.million of the $3 million total <br />project cost remained unfunded for the next phase, the project was still included <br />in the Federal Appropriation Bill currently before Conference Committee in the <br />House, anticipated for a decision by year-end. <br />Discussion included reallocation of project costs ..based on grant funds received; <br />advertising to the public by Metro Transit of the new Park and Ride facility and <br />its location. <br />Chair DeBenedet suggested that staff look into pavement design for round abouts, <br />noting his observation of some pavement breaking up at other round abouts (i.e., <br />Hudson, WI and Medford, MN) and .based on pavement stress based on truck <br />movements. <br />Other project updates included TH 280 /Paper Calmenson Sanitary Sewer with <br />completion of the gravity line connecting Paper Calmenson to the City of <br />Lauderdale; pending. demolition of the lift station; Watermain Replacement <br />Project and connection. of new service lines and abandonment of backyard service <br />lines; and the Rosewood Neighborhood Drainage Improvements south of Midland <br />Hills Golf Course. retrofitting twenty (20) raingardens in a residential <br />Mr. Schwartz provided an update of the Rice Street Bridge Reconstruction with <br />review completed of the 60% plans and a management meeting scheduled in <br />December with anticipated completion of review of the 90% plans by year-end. <br />Discussion included clear zones and delineating sidewalks; median construction <br />and aesthetics; inclusion of trees in wider median areas; cost participation for on- <br />street bike accommodations based on previous discussions of the PWET <br />Commission and City Council with the first iteration allocating those costs to the <br />City of Roseville for additional street width and associated costs. <br />Further discussion included sidewalk design and bicycle lanes; and general <br />consensus of the Cities of Roseville, Maplewood and Little Canada that Active <br />