Laserfiche WebLink
ARDEN HILLS CITY COUNCIL—JUNE 26, 2017 5 <br /> Public Works Director/City Engineer Polka stated WSB completed the plans and bid <br /> documents for a fee of $5,000 as previously approved at the April 10, 2017, City Council <br /> meeting. The scope and fee for Construction phase services was reviewed and is proposed to be <br /> completed for an hourly not to exceed fee of$62,314.00, which includes full-time construction <br /> observation, mileage reimbursement for the inspector and a 2-year warranty inspection. <br /> MOTION: Councilmember McClung moved and Councilmember Holden seconded a <br /> motion to Approve the scope and fee from WSB & Associates in the amount <br /> of $62,314.00 for construction services for the 0.5 MG north water tower <br /> repair and repainting (City Proiect No. 12-W-001). The motion carried (5- <br /> C. Planning Case 17-013 — Boston Scientific — 4100 Hamline Avenue — PUD <br /> Amendment <br /> Senior Planner Bachler stated Boston Scientific has requested a Planned Unit Development <br /> (PUD) Amendment to construct a 5,330-square foot building addition on the northeast corner of <br /> Building 9 on their campus. The Boston Scientific campus at 4100 Hamline Avenue North <br /> operates under a PUD that was originally approved in 2002 for the Guidant Corporation. The last <br /> comprehensive update to the PUD and Campus Master Plan took place in 2015 when the City <br /> approved a subdivision of the property to help facilitate the sale of Buildings A, B, and C located <br /> in the southwest corner of the campus. The Campus Master Plan was revised at that time to make <br /> adjustments to the location of future buildings and parking ramps so that the two lots could <br /> function independently. <br /> Senior Planner Bachler reported new building construction or site modifications identified on <br /> the approved Campus Master Plan require a Site Plan Review prior to construction. For building <br /> construction or site modifications not on the Master Plan, a PUD Amendment is required. The <br /> proposed addition to Building 9 is not shown on the current Master Plan and a PUD Amendment <br /> is therefore being requested. <br /> Senior Planner Bachler explained the proposed addition is for a new and expanded sterilization <br /> facility in Building 9. The company's existing sterilization facility is located in Building C and <br /> its relocation to Building 9 is part of a process that has been underway for the past several years <br /> to move operations out of Buildings A, B, and C to allow for their eventual sale. The facility will <br /> be used for the sterilization of medical products manufactured by Boston Scientific. <br /> Senior Planner Bachler commented the addition would be located on the northeast corner of <br /> Building 9, which is located in the northeast corner of the campus adjacent to Cummings Park <br /> Drive and Lexington Avenue North. The sterilization facility would have a footprint of 4,927 <br /> square feet measuring approximately 97 feet in length and 46 feet in width. The location of the <br /> addition would impact an existing parking area on the north side of Building 9. As a result of the <br /> construction, eight parking stalls would be removed. The project would also include 3,400 square <br /> feet of interior renovations for the new sterilization facility. <br /> Senior Planner Bachler stated the addition would be approximately 15 feet in height with a <br /> mechanical penthouse extending an additional 13.5 feet above the roof deck on a portion of the <br /> structure. The addition would be constructed with reinforced masonry material. Exterior finish <br /> materials would include translucent fiberglass, synthetic stucco, and metal profile panels. <br />