Page 2 of 2 <br /> <br /> <br /> <br />The project is approximately 36% complete with the reclamation area complete. Wa termain and <br />storm sewer in the Floral neighborhood are complete, and grading is underway. Watermain <br />work in the Indian Oaks neighborhood is underway. Five percent is being withheld from the <br />work completed in accordance with the contract documents. The third payment is in the amount <br />of $415,613.28. WSB has provided a recommendation to pay the third voucher (Attachment B). <br />Staff recommends that Council approve Payment No. 3 (Attachment C). <br /> <br /> Attachments <br />Attachment A: Change Order No. 2 <br />Attachment B: WSB Letter – Payment No. 3 & Change Order No. 2 <br />Attachment C: Payment No. 3 <br />