ATTACHMENT C
<br />2021 PMP - Neighborhood Portion of Project Only
<br />Arden HIlls, Minnesota
<br />Project Number PW-21-0100
<br />Item No.Item Unit Unit Price Est. Quantity Total Price
<br />2011.601 VIBRATION MONITORING LS 4,000.00 1.00 4,000.00
<br />2021.501 MOBILIZATION LS 132,000.00 1.00 132,000.00
<br />2101.502 CLEARING TREE 400.00 12.00 4,800.00
<br />2101.507 GRUBBING TREE 400.00 12.00 4,800.00
<br />2101.604 CLEAR AND GRUB BRUSH SQ YD 11.25 1,000.00 11,250.00
<br />2540.602 TEMPORARY MAILBOX BANK EACH 35.00 138.00 4,830.00
<br />2540.602 RELOCATE/REINSTALL MAILBOX EACH 135.00 138.00 18,630.00
<br />2563.601 TRAFFIC CONTROL LS 15,000.00 1.00 15,000.00
<br />SUBTOTAL - GENERAL AND REMOVALS 195,310$
<br />ENG. DESIGN, ADMIN, CONTINGENCY (20%)39,062$
<br />TOTAL - GENERAL AND REMOVALS 234,372$
<br />2104.501 REMOVE CONCRETE CURB AND GUTTER LIN FT 4.00 700.00 2,800.00
<br />2104.505 REMOVE CONCRETE DRIVEWAY APRON SQ YD 10.00 1,128.00 11,280.00
<br />2104.505 REMOVE CONCRETE DRIVEWAY PAVEMENT SQ YD 10.00 1,044.00 10,440.00
<br />2104.505 REMOVE BITUMINOUS PAVEMENT SQ YD 3.00 17,020.00 51,060.00
<br />2104.505 REMOVE BITUMINOUS DRIVEWAY PAVEMENT SQ YD 6.00 1,044.00 6,264.00
<br />2104.513 SAWING BITUMINOUS PAVEMENT (FULL DEPTH)LIN FT 4.00 400.00 1,600.00
<br />2104.523 SALVAGE SIGNS EACH 50.00 20.00 1,000.00
<br />2105.501 COMMON EXCAVATION (EV)(P)CU YD 18.00 11,344.00 204,192.00
<br />2105.507 SUBGRADE EXCAVATION CU YD 13.00 1,000.00 13,000.00
<br />2105.522 SELECT GRANULAR BORROW (CV)CU YD 25.00 5,685.00 142,125.00
<br />2105.523 COMMON BORROW (CV)(P) CU YD 2.15 1,000.00 2,150.00
<br />2105.543 STABILIZING AGGREGATE TON 39.00 50.00 1,950.00
<br />2105.602 POTHOLE EXISTING UTILITIES EACH 535.00 8.00 4,280.00
<br />2123.501 COMMON LABORERS HOUR 83.00 10.00 830.00
<br />2123.507 3.0 CU YD SHOVEL HOUR 182.00 10.00 1,820.00
<br />2123.61 STREET SWEEPER (WITH PICKUP BROOM)HOUR 152.00 15.00 2,280.00
<br />2130.501 WATER FOR DUST CONTROL M GALS 34.00 70.00 2,380.00
<br />2211.501 AGGREGATE BASE, CLASS 5 TON 18.00 6251.175 112,521.15
<br />2232.501 MILL BITUMINOUS SURFACE (3.0")SQ YD 3.10 8,845.00 27,419.50
<br />2301.604 PRIVATE DRIVEWAY CONCRETE PAVING SQ YD 68.25 1,044.00 71,253.00
<br />2331.604
<br />AGGREGATE BASE, CLASS 7, FULL DEPTH
<br />RECYCLED PRODUCTION SQ YD 1.10 8,845.00 9,729.50
<br />2357.502 BITUMINOUS MATERIAL FOR TACK COAT GALS 3.50 1,293.05 4,525.68
<br />2360.501 TYPE SPWEB240C WEARING COURSE MIXTURE TON 65.00 5,630.00 365,950.00
<br />2360.503 3.0 IN. WEARING COURSE MIXTURE FOR DRIVEWAYS SQ YD 30.00 1,044.00 31,320.00
<br />2521.501
<br />6-INCH CONCRETE WALK - PEDESTRIAN CURB
<br />RAMPS SQ FT 11.75 120.00 1,410.00
<br />2531.501 CONCRETE CURB AND GUTTER, DESIGN B618 LIN FT 14.00 8,510.00 119,140.00
<br />2531.501
<br />CONCRETE CURB AND GUTTER, DESIGN B618 -
<br />HAND FORM LIN FT 29.85 1,000.00 29,850.00
<br />2531.507 6-INCH CONCRETE DRIVEWAY PAVEMENT SQ YD 61.25 1,128.00 69,090.00
<br />2531.618 TRUNCATED DOMES SQ FT 55.00 32.00 1,760.00
<br />2564.537 INSTALL SALVAGED SIGNS, TYPE "C"EACH 120.00 20.00 2,400.00
<br />2582.502 4" SOLID LINE - PAINT LIN FT 1.30 4,600.00 5,980.00
<br />2582.502 4" DOUBLE YELLOW - PAINT LIN FT 2.10 2,300.00 4,830.00
<br />2582.502 24" STOP LINE - PAINT LIN FT 12.20 84.00 1,024.80
<br />SUBTOTAL - STREET IMPROVEMENTS 1,317,655$
<br />ENG. DESIGN, ADMIN, CONTINGENCY (20%)263,531$
<br />TOTAL - STREET IMPROVEMENTS 1,581,186$
<br />GENERAL AND REMOVAL
<br />STREET IMPROVEMENTS
<br />Page 1 of 3
|