Laserfiche WebLink
Page 2 of 2 <br /> <br /> <br />Budget Impact <br /> <br />The revised construction contract amount and overall budget for the Colleen Avenue Drainage <br />Improvements project is summarized below. <br /> <br />Original Contract Amount:250,247.00$ <br />Change Order No. 1 2,800.00 <br />Change Order No. 2 2,456.00 <br />Change Order No. 3 2,897.10 <br />Change Order No. 4 1,100.00 <br />Change Order No. 5 880.00 <br />Completed contract difference (436.75) <br />Amended Contract Amount:259,943.35 <br />Engineering Design 42,142.00 <br />Construction Administration 33,000.00 <br />Other costs 3,256.08 <br />Total Project Costs:338,341.43$ <br />(3.98% Over Budgeted Amount) <br />The entire cost of this project is funded by the Surface Water Management Fund. <br /> <br />Attachments <br /> <br />Attachment A: Bolton & Menk Letter with Final Pay Request <br />Attachment B: Change Order No. 5 <br /> <br /> <br /> <br />