Laserfiche WebLink
<br />I <br />.. PROJECT SCHEDULE <br /> The following project schedule could be implemented for construction of the <br />I Keithson Area Holding Pond and Storm Sewer Outlet Improvements. <br />I Task Date <br /> Receive Feasibility Study, Approve Plans February 10, 1992 <br />I and Specifications, Accept Bids and Order <br /> Public Hearing <br />I Hold Public Hearing, Establish Amount to be March 9, 1992 <br /> Assessed, Set Assessment Hearing Date and <br /> Award Contract <br />I Begin Construction March 23, 1992 <br /> Hold Assessment Hearing Ap ril 13, 1992 <br />I End Construction Apri 1 23, 1992 <br />I CONCLUSION <br />.. The estimated total project cost of the storm sewer improvements to serve <br /> the Keithson Pond to provide an outlet is $47,600. The project is feasible <br />I from an engineering standpoint. <br />I <br />I <br />I <br />I <br />I <br />I. <br />I <br /> 7 <br />I <br /> ----- <br />