Page 2 of 3 <br />Following City Council approval, the project was sent to seven contractors on Thursday, <br />February 13, 2025, inviting them to provide a quote for the project. Five quotes were received on <br />March 5, 2025. Two bidders reached out and stated that due to the small scope of the project they <br />would not be interested in bidding. The following is a summary of the bids received: <br /> <br /> Bidders Total Base Bid Bid Alternate <br />1 Albrecht $117,603.00 $41,560.00 <br />2 Pember $129,959.00 $41,428.20 <br />3 Dunaway $132,803.90 $63,053.40 <br />4 Peterson Companies $143,906.80 $52,923.90 <br />5 Urban Companies $154,911.00 $47,761.00 <br /> <br />City staff and the consultant reviewed the bids, which came in higher than anticipated. Knowing <br />that this was a smaller project and higher than anticipated costs were likely, staff and the <br />consultant reviewed areas of the project that could be handled in-house or with the ICWC work <br />crew as a cost savings measure. <br /> <br />Staff felt that the removal of the playground equipment and safety surface material (existing <br />engineered wood fiber) removal could be done in-house for a savings of approximately <br />$31,250.00. City maintenance staff was part of the discussion and indicated they could <br />reprioritize their workload to accommodate these tasks. <br /> <br />After additional investigation, the consultant found a group to remove both playgrounds at no <br />cost to the city. Based on this arrangement, city maintenance staff would only need to remove <br />and dispose of the existing engineered wood fiber surfacing material. <br /> <br />Discussions with the low bidder, Albrecht Company, were had to make sure they were amenable <br />to the changes in the bid, which they were. With the changes mentioned above, the adjusted <br />contract bid amount is $86,353.00. <br /> <br />Bid Alternate <br />Included in the plans was a bid alternate for additional improvements to Arden Oaks Park that <br />included an ADA bituminous trail connection from Arden Oaks Drive to the playground <br />containers, as well as a portable restroom enclosure, and concrete pad for trash receptacles. <br />While there is a desire to provide an accessible route to the playground containers at Arden Oaks <br />(new playgrounds are designed to be all-inclusive and ADA accessible), it was included as an <br />alternate bid to allow for flexibility in the composition of the overall project depending on <br />bidding results. Pricing for the alternate bid are included in the table above. Due to the project <br />costs as-bid, staff recommends budgeting for and completing the alternate bid work at Arden <br />Oaks in 2026. <br />Budget Impact <br /> <br />Actual Project Costs: <br />PSA – Public Engagement and Project Scope $12,419.00 <br />PSA – Design & Construction Administration $79,586.00 <br />Arden Oaks Park Construction $48,638.00 <br />Arden Oaks Playground Structure $172,178.00 <br />Arden Oaks Swing Addition $4,948.78 <br />Freeway Park Construction $37,715.00 <br />Freeway Park Playground Structure $150,434.00 <br />Total Project Costs to Date $505,918.78