Page 2 of 2 <br /> <br />• Lake Johanna Blvd. <br />o 3 phased project approach. <br /> Planning/Design – 2026. <br /> Phase 1 construction – 2029. <br /> Phase 2 construction – 2030. <br /> Phase 3 construction – TBD. <br /> <br />• Spine Road proposed cost share/funding strategy. <br />o County to fully fund the project including all City water/sewer utilities. <br />o Same agreement type and approach to the “Thumb Road” construction project. <br />o County to recoup costs through land sale. <br />o Cooperative Agreement between Ramsey County and City of Arden Hills is being <br />drafted. <br /> <br />Budget Impact <br /> <br />The City Council should consider the information provided and give direction to City staff to <br />make any adjustments to the current proposed 2026-2030 CIP. <br /> <br />Attachments <br /> <br />N/A