<br />c. <br /> <br />Project Schedule <br /> <br />The following schedule has been prepared based upon City Council receiving this <br />feasibility report on November 12, 2002: <br /> <br />Receive Feasibility ReporUSchedule Public Hearing <br />Public Hearing/Order Plans and Specs <br />Assessment Hearing <br />Approve Plans and Specifications/Authorize <br />Advertisement for Bid <br />Bid Opening <br />Award Contract <br />Begin Construction <br />Complete Construction <br /> <br />November 12, 2002 <br />November 26,2002 <br />Febmary 24, 2003 <br /> <br />March 10,2003 <br />April 17, 2003 <br />April 28, 2003 <br />May 19,2003 <br />August 30, 2003 <br /> <br />It should be noted that although the entire projected construction period is over three <br />months, the project specifications will require that the Contractor restore streets with <br />curb and gutter and one lift of bituminous within 28 days of the initial removal of the <br />existing pavement on a given street. The contract will also stipulate that all <br />neighborhood streets will be passable at all times during the constmction period for <br />local traffic, <br /> <br />D. <br /> <br />Summary <br /> <br />The Ingerson Neighborhood and the Karth Lake East neighborhood are at the top of <br />the City's priority lists for pavement reconstmction and pavement rehabilitation work <br />respectively. The Ingerson neighborhood pavements do not meet city standards and <br />continue to deteriorate at a steady pace, Several drainage issues exist within the <br />neighborhood due to substandard drainage systems or no drainage infrastmcture at all. <br />Runoff from the neighborhood flows untreated into natural water bodies including <br />Lake Josephine, The Karth Lake East neighborhood pavements are approximately 24 <br />years old and are in need of rehabilitation before the pace of their deterioration <br />accelerates. <br /> <br />The improvements outlined in this report will bring the Ingerson neighborhood up to <br />standards and bring new pavement life into the Karth Lake East neighborhood, Equally <br />important, the proposed drainage improvements will enhance the water quality of Lake <br />Josephine, Lake Johanna and Karth Lake within the City of Arden Hills, <br /> <br />Project costs, as illustrated herein, are reasonable and representative of the proposed <br />scope of improvements. Although the overall cost of the proposed 2003 PMP <br />Improvements Project is significant, the City has not invested a significant amount of <br />funding into the City's pavement and drainage infrastructure since 1998 and therefore <br />the City's State Aid balance has grown substantially as have the general funds annually <br />earmarked for PMP projects, The scope of the project should also help the City realize <br /> <br />t8 <br /> <br />I <br />J <br />I <br />I <br />I <br />I <br />I <br />I <br />I <br />. <br />I <br />I <br />I <br />I <br />I <br />I <br />I <br />, <br />I <br />