<br />Application for Payment: Itemization
<br />eChedule: A - LIFT STATION #7 Unit Contract Contract To-Date To-Date
<br />No. Item Unit Price Quantity Amount Quantity Amount
<br />1 MOBILIZATION LS $4,590.00 1.00 $4,590,00 1.00 $4,590,00
<br />2021.501
<br />2 LIFT STATION NO, 7 REMOVAL LS $4,800,00 1.00 $4,800,00 1.00 $4,800,00
<br />2103.601
<br />3 REMOVE SEWER PIPE (6' CIP) LF $10.00 15.00 $150,00 15,00 $150,00
<br />2104.501
<br />4 REMOVE SEWER PIPE (8' VCP) LF $10.00 30,00 $300,00 30,00 $300.00
<br />2104.501
<br />5 REMOVE MANHOLE (SANIT ARYl EA $1,000,00 1.00 $1.000.00 1,00 $1,000.00
<br />2104.509
<br />6 OEWATERING LS $3,000,00 1.00 $3,000,00 0.34 $1,020.00
<br />2451.601
<br />7 8' PVC PIPE SEWER LF $60.00 15,00 $900,00 20,00 $1,200.00
<br />2503.503
<br />8 FITTINGS LB $3,00 2,000.00 $6,000,00 192,00 $576,00
<br />2503,503
<br />9 4' DIP FORCEMAIN, Cl50 LF $25,00 40.00 $1,000,00 45,00 $1,125.00
<br />2503.503
<br />10 6' DIP FORCEMAIN, Cl50 LF $30,00 15.00 $450,00 32,00 $960,00
<br />2503.503
<br />11 4' FlANGE GATE VALVE EA $345,00 2,00 $690,00 2,00 $690.00
<br />2503.503
<br />. 6'FlANGEGATEVALVE EA $520,00 2.00 $1,040.00 2,00 $1,040.00
<br /> 3.503
<br />3 CONNECTTO EXISTING SANITARY SEWER EA $500,00 2.00 $1,000,00 2,00 $1,000,00
<br />2503.503
<br />14 4' SWING FLEX CHECK VALVE EA $435,00 2,00 $870.00 2,00 $870,00
<br />2503.503
<br />15 3' STEEL VENT PIPE EA $100.00 1.00 $100.00 1,00 $100.00
<br />2503.503
<br />16 F & I LIFT STATION NO, lELECTRICALSYSTEM LS $20,900.00 1.00 $20,900.00 1.00 $20,900.00
<br />2503.603
<br />17 F & I LIFT STATION NO, 7 PUMP SYSTEM LS $28,500,00 1.00 $28,500,00 1,00 $28,500.00
<br />2503.603
<br />18 CONNECT TO EXISTING SANITARY FORCEMAIN EA $500.00 1,00 $500,00 1.00 $500.00
<br />2503.603
<br />19 SEWER BYPASS LIFT STATION #7 LS $6,012.00 1,00 $6,012,00 1.00 $6,012.00
<br />2503.603
<br />20 7'Z LIFT STATION WET WELL WITH ACCESS EA $24,763.00 1,00 $24,763,00 1.00 $24,763,00
<br /> HATCH
<br />2506.602
<br />21 60" VALVE MANHOLE EA $5,508,00 1,00 $5,508,00 1,00 $5,508,00
<br />2506.602
<br />22 TEMPORARY CONSTRUCTION FENCE LF $4,00 800.00 $3,200.00 75,00 $300,00
<br />2573.502
<br />23 SILT FENCE TYPE HEAVY OUTY LF $3,00 600,00 $1,800,00 175.00 $525.00
<br />2573.502
<br />24 SOODING TYPE LAWN SY $4.00 3,000,00 $12,000.00 3,000,00 $12,000.00
<br />_,.505
<br /> RESTORATION LS $5,000.00 1,00 $5,000,00 1,00 $5,000,00
<br />2575.602
<br /> Subtotal: $134,073.00 $123,429,00
<br /> Page 3 of 5