My WebLink
|
Help
|
About
|
Sign Out
Home
Browse
Search
CCP 12-13-2004
ArdenHills
>
Administration
>
City Council
>
City Council Packets
>
2000-2009
>
2004
>
CCP 12-13-2004
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
5/8/2007 1:19:55 PM
Creation date
11/14/2006 3:36:51 PM
Metadata
Fields
Template:
General (2)
Jump to thumbnail
< previous set
next set >
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
280
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
<br />. <br /> <br />. <br /> <br />. <br /> <br />Attachment to Change Order No.1 <br />URS Job No. 37951-023-0101 <br /> <br />Owner: <br />Contractor: <br />Project: <br /> <br />City of Arden Hills <br />Amt Construction Company, Inc. <br />2003 Pavement Management Program <br /> <br />Description of changes: <br /> <br />Several additions and modifications were made to the project plans as a result of field comments and <br />requests made by the City of Arden Hills and the engineer during construction of the projecl. These minor <br />revisions were made to several different areas of the plans. As a result of these modifications, the scope of <br />the project was increased, as well as the original contract amount for the work. The following is an <br />overview of the modifications made to the contract: <br /> <br />Item # 1- Additional Undere.round Utility Work <br /> <br />The engineer requested the contractor to perform a variety of additional utility work throughout the process <br />of construction. This work was required to accommodate the proposed utility installation, as well as <br />eliminate future maintenance issues for the city. This work was performed on a time and material basis. <br />Specific Work Orders are included with this Change Order for documentation. The scope of this additional <br />utility work is as follows: <br /> <br />STORM SEWER <br />^) Field adjustments. to manhole D-2 due to conflicts with in-place private utilities. <br />B) Re-alignment of manholes STS-2 and STS-3 due to conflicts with in place private utilities. <br />C) Modify catch basins CB-2, CB-3, CB-14 and CB-17 to avoid existing 6" steel gas main, <br />D) Modify proposed storm structures. along Ingerson Road at Femwood Street, as well as along <br />Cannon A venue at Tiller Lane as existing in-place utilities differed from as-built information. <br />E) Miscellaneous minor field modifications to CBMH 30, CBMH 19, and CBMH 12. These changes <br />were made to accommodate a field changes to. the road profiles. <br /> <br />Cost of Storm Sewer Work = $16,433.88 <br /> <br />SANITARY SEWER <br />A) Exploratory excavation along Ingerson Road to verify existing utility locations. <br />B) Relocate existing sanitary service at Fernwood Ct. to avoid a conflict with the proposed storm <br />sewer. <br /> <br />Cost of Sanitary Sewer Work = $10,851.87 <br /> <br />W A TERMAIN <br />A) Expose existing water main along Amble Drive. Unable to shut down gate valve. <br />D) Remove. furnished and install a new gate valve along Amble Drive at Amble Circle. <br />C) Performed a wafer main offset at STS-3 to avoid conflict with proposed storm sewer. <br />D) Remove and replace unsuitable material in roadway (Amble Dr.) at damaged gate valve. <br />E) Perform a water main offset along Ingerson Road at Fernwood Street to avoid a conflict with the <br />proposed storm sewer. <br />F) Removed, furnished and installed a new gate valve along Ingerson Road at Fernwood Street. <br />G) Exploratory excavation along Ingerson Road to verify existing utility locations. <br /> <br />Cost of Water main Work = $43,338.88 <br /> <br />Total Cost of Item # 1 <br /> <br />$70,624.63 <br /> <br />20f3 <br />Change Order No. ) <br />
The URL can be used to link to this page
Your browser does not support the video tag.