Laserfiche WebLink
<br />CHANGE ORDER NO.2 <br /> <br /> <br />ram <br /> <br />URS Job No.: 37951-027-0101 <br /> <br />Owner: <br /> <br />City of Arden Hills <br />1245 West Highway 96 <br />Arden Hills, MN 55112 <br /> <br />Date ofIssuance: August 29, 2005 <br /> <br />Contractor: <br /> <br />Amt Construction, Inc. <br />P.O. Box 549 <br />Hugo, MN 55038 <br /> <br />Engineer: URS Corporation <br />Thresher Square Building <br />700 Ibird Street South <br />Minneapolis, MN 55415 <br /> <br />Description of Change Order: The contract has been modified to include payment for additional work associated with <br />the replacement of existing watermain pipe along Edgewater Avenue and poor subgrade soils. This work was required due <br />to the poor condition of the water main observed during excavation. Much of the material excavated for watermain <br />trcnching was of poor quality and not suitable for recompaction into the trench and was removed from the site and <br />. replaced with suitable materials. The additional work will reduce the potential for significant watermain issues in the <br />Edgewater neighborhood. This work was performed at negotiated prices or contract unit prices where applicable. The <br />additional work also includes furnishing and installing temporary water services for the 21 residences affected by the <br />watermain shutdown. on under roadways and watermain trenches and pond excavation required by Rice Creek Watershed <br />District. The individual items associated with this additional work are as follows: <br /> <br />A) Remove curb stop and box 14EA @ $55.00EA ~ $770.00 <br />B) Reconnect water service 14EA@ $275.00EA ~ $ 3,850.00 <br />C) I" Curb Stop -14@ $165.00 ~ $ 2,310.00 <br />D) Temporaty water services 21EA @ $825.00 ~ $17,325.00 <br />E) Repair outside water spigots 6EA @ $165.00 ~ $990.00 <br />F) Watermain Fittings 700 LB @ $3.20 ~ $2,240.00 <br />G) Connect to Existing Watermain 4 EA@ $1,260.00 ~ $5,040.00 <br />H) Subgrade Excavation 1,700 CY @ $11.46 ~ $19,482.00 <br />I) 48" Manhole Catchbasin !5 LF@ $240.00 ~ $3,600.00 <br /> <br />Total Work Change Order No.2 <br /> <br />$55,607.00 <br /> <br />Thc additional work will be funded through the watermain utility, storm drainage and street funds. <br /> <br />Recommended <br /> <br />Approved <br /> <br />By: <br /> <br />By: <br /> <br />URS Corporation <br /> <br />Amt Construction, Inc. <br /> <br />Approved By: <br /> <br />City of Arden Hills <br /> <br />. <br />