<br />Table 4-11
<br />MnDOT Highway Work Plan, 2009-2013
<br />Major Construction, Reconstruction and Bridge Replacement Greater Than $10 Million
<br />
<br /> Proiect Cost Estimates
<br /> Design R1W Year-of- Construction Total
<br /> Project Construction Estimate Estimate Construction Engineering Project
<br />Highw3)' Description Program Fiscal Year ($000) ($000) Estimate Estimate Cost
<br /> ($000) ($000) ($000)
<br />35E ]-94 to Maryland MC 2010 7.687 Limited 76.755 6,140 90,57]
<br /> Ave. in St. Paul,
<br /> grading, surfacing,
<br /> brs., etc., including
<br /> Cayuga Br. and
<br /> Phalen Blvd.
<br /> connection
<br />35W At Lake St. in MC 2009 1,]60 Contin- 1],600 928 13,688
<br /> Minneapolis, liDUS/
<br /> reconstruct inter- Major
<br /> change (Ph. I)
<br />35W At Lake St. in MC 20]0 1,785 Contin- 17.850 1.428 21.063
<br /> Minneapolis, liOUS/
<br /> reconstruct inter- Major
<br /> change (Ph. 2)
<br />36 At Lexington MC 2009 1,380 Limited 13,804 1,]04 16,289
<br /> Ave.. in RoseviIJe,
<br /> replace Bf. 5723
<br /> and reconstruct
<br /> interchange
<br />100 36lh St. to Cedar MC 2011 6,150 Contin- 61,500 4,920 72,570
<br /> Lake Rd. in St. liOUS/
<br /> Louis Park, Major
<br /> grading, surfacing,
<br /> Brs., etc. for 6-lane
<br /> freeway
<br />169 Near CSAH 6 in MC 2010 ],904 Limited 19,040 1,523 22.467
<br /> Belle Plaine,
<br /> grading, surfacing,
<br /> Br., etc. for new
<br /> interchange
<br />694 E of135W in MC 2012 6,960 Minimall 69,596 5,568 82,]23
<br /> Arden Hills to E of Spot
<br /> Lexington Ave.. in
<br /> Shoreview,
<br /> grading, surfacing,
<br /> Brs., etc. to add
<br /> third lane and
<br /> correct weave at
<br /> TH 10/51
<br /> TOTALS 27,015 270,145 21,611 318,771