MEMORANDUM
<br /> Rice Creek Watershed District
<br /> Date: May 17, 2018
<br /> To: RCWD Board of Managers
<br /> From: Samantha Berger, District Technician
<br /> Subject: AMEND A17-08 and A18-01 City of Centerville Trailside Park Shoreline Stabilization
<br /> RCWD Water Quality Grant Program Application
<br /> AMEND A17-08 City of Centerville Shoreline Stabilization
<br /> • Location:Trailside Park, 7145 Main St, Centerville, MN
<br /> • Project Type: Shoreline Stabilization
<br /> • Total Eligible Project Cost: $22,420
<br /> • RCWD Cost-Share Provided: $16,815 (75%) +Amendment—See Options below
<br /> AMEND A18-01 City of Centerville Trailside Park Phase 2 Shoreline Stabilization
<br /> • Location:Trailside Park, 7145 Main St, Centerville, MN
<br /> • Project Type: Shoreline Stabilization
<br /> • Total Eligible Project Cost: $23,120
<br /> • RCWD Cost-Share Provided: $11,560 (50%) +Amendment—See Options below
<br /> BACKGROUND
<br /> The District Board has approved 2 phases of a shoreline restoration project totaling 678 linear feet off
<br /> Centerville Lake in Centerville, MN. The project is nearing completion; however, based on onsite
<br /> conditions as described in the attached Anoka Conservation District memo,the project will require
<br /> additional rock to stabilize the shoreline properly and to ensure the longevity of the project.The City is
<br /> requesting whether additional funds would be available from the District to cover the additional
<br /> $21,840 needed to complete the project.
<br /> District Staff and the Conservation District are very supportive of the project and recommend providing
<br /> additional funds to cover the overage. Below, staff has outlined 3 different funding options. Obviously,
<br /> a 4t"option would be to not approve additional dollars; however, Staff does not recommend this
<br /> approach. The highlighted number represents the total added cost for the project for each option and
<br /> the total costs for the City and District. Notably,the "Overage Amount" represents the cost of the
<br /> additional rock for each phase under different options.
<br /> Option 1:Amend Agreements for Phase 1 and Phase 2(A17-08 at 75% and A18-01 at 50%,
<br /> respectively) respective to the grant percentage approved by the Board.This would be an $11,250
<br /> amendment for A17-08 and a $3,420 amendment for A18-01. District Total Cost: $43,045 (64%)
<br /> Total Project ApprovedOverage Amendment°% Amendment
<br /> Phase City Cost District
<br /> Cost.. Cost Amount District Cost.. °%..City Cost
<br /> Phase 1 $22,420 $5,605 $16,815 $15,000 $11,250 (75%) $3,750 (25%)
<br /> (A17-08) (75%)
<br /> Phase 2 $23,120 $11,560 $11,560 $6,840 $3,420 (50%) $3,420 (50%)
<br /> (A18-01) (50%)
<br /> Totals to $45,540 $17,165 $28,375 $21,840 $14,670 $7,170
<br /> Date
<br /> Overage
<br /> Option 1 $21,840 (+$7,170) (+$14,670)
<br /> Totals 380 $24,335 $43,045'
<br /> w/Overage $67, (36%) (64°%)
<br /> Page 1