CENTENNIAL STATION 3 RENOVATION SCOPE OF WORK TIMELINE <br />Total Project Time — 21 days <br />Phase 1: Removal of Office Area (CFD) — 3 days <br />o Pack and move EMS items <br />o Pack and move EMS cubicle in preparation to transport to Station 1 radio room <br />o Disconnect electrical from cubicle <br />o Pack and move Inspector items <br />o Pack and move Inspector's cubicle in preparation to install in Station 3 radio room <br />o Disconnect electrical from cubicle <br />o Pack and move any file cabinets that Station 1 would want <br />o Recycle/remove any broken/unneeded file cabinets and items <br />Phase 2: Demolition of Existing Wall (CFD) — 2 days <br />o Removal of all wall art and decor <br />o Disconnect (4) existing outlets and (1) light switch <br />o Temporary relocate thermostat <br />o Demolition of existing wall up to the tile floor <br />o Save electrical wiring, piping and outlets <br />Phase 3: Installation of New Wall (Imperial Wall) — 4 days <br />o Delivery/stocking <br />o 3 5/8" metal stud walls to 8'0" grid <br />o 5/8" type "X" gypsum board <br />o Zip trim at top od wall and outside corner bead <br />o 3 coat tape and sand <br />o Minor touch up of existing walls <br />Phase 4: Accent Wall (CFD) — 2 days <br />o Installation of (4) 48" x 96" new wood paneling on TV wall <br />o Cure time minimum of 24 hours <br />Phase 5: Electrical (CFD) — 3 days <br />o Install (1) outlet on accent wall behind where the TV will be mounted <br />o Install (1) HDMI outlet on accent wall behind where the TV will be mounted <br />o Install (1) outlet on new wall near where the podium will be located <br />o Install (1) HDMI outlet on new wall near where the podium will be located <br />o Install (1) light switch on new wall to control front half of ceiling lights in TV area <br />o May require relocating ceiling lights to different ceiling tile locations <br />o Relocate thermostat near corner of new wall <br />o Rewire light in storage area to run off single switch <br />o Rewire light in kitchen area to run off single switch <br />Phase 6: Painting (CFD) — 2 days <br />o Fill any necessary holes in block walls and sheetrock walls <br />o New paint throughout area <br />