Laserfiche WebLink
Phase 7: TV Installation (CFD) —1 day <br />o Installation of new 75" TV with wall mount <br />o Relocate cable box from existing TV to new TV <br />o Remove existing TV <br />o Remove existing TV outlet <br />Phase 8: Carpet Installation (CFD) — 2 days <br />o Removal of existing carpet <br />o Installation of new carpet tiles <br />Phase 9: Wall Decor and Art Work (CFD) —1 day <br />o Installation of (2) Honor Guard Pike Poles on each side of the TV <br />o Installation of CFD patch on the right side of the TV <br />o Installation of custom Station 3 Maltese cross on the left side of the TV (paint Maltese black or red) <br />o Place American Flag in the left corner of the accent wall <br />o Installation of new 5' x 3' white board on new wall <br />o Installation of (2) Honor Guard Axes between the windows on the south wall <br />o Installation of Centerville Fire Dept. history items on existing wall perpendicular to new wall <br />o Remove existing white board on east wall and relocate to radio room <br />o Relocate current firefighters board to east wall <br />o Installation of (1) large coat hook rack on east wall near entry door <br />Phase 10: Acquire new tables and chairs (CFD) — 1 day <br />o (8) new collapsible/storage tables <br />o (24) new chairs <br />