<br /> . -
<br /> Contract Unit Quantity Amount
<br />No. Item Unit Quantity Price to Date to Date
<br /> Part 1 - Sanitary Sewer
<br />1 Mobilization LS 1 34000.00 0.95 $32,300.00
<br />2 8" PVC sanitary sewer, SOR 35, 8'-10' deep LF 225 25.85 225 $5,771.25
<br />3 8" PVC sanitary sewer, SOR 35, 10'-12' deep LF 100 25.65 100 $2,565.00
<br />4 8" PVC sanitary sewer, SOR 35, 12'.14' deep LF 705 25.65 705 $18,083.25
<br />5 8" PVC sanitary sewer, SOR 35,14'-16' deep LF 340 25.65 140 $3,591.00
<br />6 12" PVC sanitary sewer, SOR 35,10'-12' deep LF 1020 27.75 1020 $28,305.00
<br />7 12" PVC sanitary sewer, SOR 35,12'-14' deep LF 1022 27.75 1022 $28,360.50
<br />8 12" PVC sanitary sewer, SOR 35, 14'-16' deep LF 570 27.75 571 $15,845.25
<br />9 4" PVC, Scl1. 40 riser pipe LF 50 19.00 57 $1,083.00
<br />10 8" PVC forcemain LF 110 24.25 110 $2,667.50
<br />11 8" x 4" PVC wye EA 23 75.00 14 $1,050.00
<br />12 12" x 4" PVC wye EA 14 130.00 21 $2,730.00
<br />13 4' diameter sanitary MH. 8' deep EA 19 1900.00 19 $36,100.00
<br />14 4' diameter sanitary manhole over depth LF 76 145.00 76 $11,020.00
<br />15 Construct manhole over existing pipe EA 1 2100.00 1 $2,100.00
<br />16 Improved pipe foundation LF 3982 1.90 2551 $4,846.90
<br />17 Seedin9 AC 1 1300.00 $0.00
<br />18 Closed circuit TV inspection LF 3982 0.60 $0.00
<br />19 Clearing and grubbing LS 1 SODO.OO 1 $5,000.00
<br /> Total Part 1 - Sanitary Sewer $201,418.65
<br /> Part 2 ~ Water Main
<br />20 12" PVC water main LF 3220 23.00 3223 $74,129.00
<br />21 8" PVC water main LF 160 23.00 160 $3,680.00
<br />22 6" PVC water main LF 600 23.00 557 $12,811.00
<br />23 12" gate valve and box EA 5 1300.00 5 $6,500.00
<br />24 8" gate valve and box EA 3 760.00 3 $2,280.00
<br />25 6" gate valve and box EA 6 565.00 6 $3,390.00
<br />26 Install hydrant EA 4 2000.00 4 $8,000.00
<br />27 Connect to existing water main EA 1 600.00 1 $600.00
<br />28 Ductile iron fittings LB 10000 0.85 10330 $8,780.50
<br />29 Improved pipe foundation LF 2000 1.90 1290 $2.451.00
<br />30 Remove bituminous driveway SY 20 2.80 $0.00
<br />31 Sawing bituminous pavement LF 20 5.00 $0.00
<br />32 3" Type 41A, bit. driveway pavement SY 20 28.65 $0.00
<br />33 Seeding AC 0.4 1300.00 $0.00
<br />34 Salvage and reinstall gravel driveway SY 830 4.00 830 $3,320.00
<br />35 Salvage and reinstall 24" RCP LS 1 670.00 1 $670.00
<br />36 A9gregate base, Class 5 TN 150 12.00 285 $3,420.00
<br />37 12" pipe restraint EA 48 115.00 48 $5,520.00
<br />38 8" pipe restraint EA 14 100.00 14 $1,400.00
<br />39 6~ pipe restraint EA 28 100.00 28 $2,800.00
<br /> Total Part 2 - Water Main $139,751.50
<br /> Part 3 - Services
<br />40 1 ~ corporation stop EA 22 125.00 22 $2,750.00
<br />41 1 ~ curb stop and box EA 22 135.00 22 $2,970.00
<br />42 1" Type "K~ copper water service LF 900 18.00 986 $17,748.00
<br />43 4" PVC, Sch. 40 service pipe LF 1000 20.00 1049 $20,980.00
<br /> Total Part 3 - Services $44,448.00
<br /> Part 4 - Storm Sewer
<br />44 12" RCP storm sewer, Class 5 LF 260 28.50 126 $3,591.00
<br />45 15" RCP storm sewer, Class 5 LF 990 30.00 315 $9,450.00
<br />46 27" RCP storm sewer, Class 3 LF 197 46.65 197 $9,190.05
<br />47 30" HOPE stonm sewer LF 134 35.00 134 $4,690.00
<br />48 18" HOPE stonm sewer LF 129 20.65 116 $2,395.40
<br />49 15~ HDPE storm sewer LF 143 17.00 127 $2,159.00
<br />50 12" HOPE stonm sewer LF 249 16.00 255 $4,080.00
<br />51 4' diameter storm CBMH EA 6 1500.00 6 $9,000.00
<br />52 5' diameter storm CBMH EA 3 2400.00 3 $7,200.00
<br />53 Skimmer structure EA 1 1100.00 1 $1,100.00
<br />54 2' x 3' catch basin EA 4 1400.00 4 $5,600.00
<br />55 30" HOPE flared end section with trash guard EA 1 1085.00 1 $1,085.00
<br />56 27" RCP flared end section, including trash guard EA 1 1300.00 1 $1,300.00
<br />57 18" HOPE flared end section with trash 9uard EA , 345.00 1 $345.00
<br />61600117REQ4,;.cls
<br />--
<br />
|