<br /> Contract Unit Quantity Amount
<br />No. Item Unit Quantity Price to Date to,Oate
<br /> Part 1 ~ Sanitary Sewer
<br />1 Mobilization LS 1 21000.00 1 $21,000.00
<br />2 Connect to existing manhole EA 1 525.00 1 $525.00
<br />3 Connect to existing sanitary sewer 8" PVC pipe EA 1 370.00 1 $370.00
<br />4 Core drill connection to existing manhole EA 1 1050.00 1 $1,050.00
<br />5 Remove and replace eXisting silt fence LF 100 3.00 $0.00
<br />6 Silt fence, regular LF 50 2.00 $0.00
<br />7 Hay bales EA 10 6.00 $0.00
<br />8 8" PVC sanitary sewer, SDR 35, 0'.10' deep LF 316 14.70 316 $4,645.20
<br />9 8" PVC sanitary sewer, SDR 35, 10'.12' deep LF 80 16.80 80 $1,344.00
<br />10 8" PVC sanitary sewer, SDR 35,12'.14' deep LF 284 18.90 314 $5,934.60
<br />11 4" PVC, Soh. 40 riser pipe LF 18 10.50 5 $52.50
<br />12 8" x 4" PVC wye EA 15 48.00 15 $720.00
<br />13 Cut 4" Service into 8" PVC EA 1 525.00 1 $525.00
<br />14 4' diameter sanitary MH, 8' deep EA 3 1575.00 3 $4,725.00
<br />15 4' diameter sanitary manhole Dverdepth LF 11.5 90.00 10 $900.00
<br />16 Improved pipe foundation, per 6" increment LF 680 3,70 680 $2,516.00
<br />17 Seeding AC 0.5 2400.00 $0.00
<br />18 Closed circuit TV inspection LF 710 1.00 $0.00
<br />19 Clear and grub LS 1 2000.00 $2,000.00
<br /> Total Part 1 - Sanitary Sewer $46,307.30
<br /> Part 2 - Watermain
<br />20 Connect to existing a" water main EA 2 420.00 2 $840.00
<br />21 Connect to existing 6" water main EA 3 315.00 3 $945.00
<br />22 a" PVC water main LF 475 18.00 475 $8,550.00
<br />23 6" PVC water main LF 461 15.75 406 $6,394.50
<br />24 12" water main offset EA 1 2940.00 1 $2,940.00
<br />25 8" water main offset EA 1 1840.00 1 $1,840.00
<br />26 6" gate valve and box, in place EA 5 650.00 5 $3,250.00
<br />27 Instali hydrant EA 5 1575.00 5 $7,875.00
<br />28 Ductile iron fittings LB 625 1.30 679 $882.70
<br />29 Improved pipe foundation, per 6~ increment LF 860 0.01 $0.00
<br />30 Insulation, 3" thick SY 60 22.00 60 $1,320.00
<br /> Total Part 2 - Watermain $34,837.20
<br /> Part 3 ~ Services
<br />31 1 N corporation stop EA 31 90.00 32 $2,880.00
<br />32 '" curb stop and box EA 31 79.00 32 $2,528.00
<br />33 1" Type "K" copper water service LF 1320 8.00 1417 $11,336.00
<br />34 1 ~ Type NK" copper water service drilled LF 90 47.25 140 $6,615.00
<br />35 Connect to existing sewer service EA 14 525.00 14 $7,350.00
<br />35 4" PVC, Sch. 40 service pipe LF 1265 7.90 1279 $10,104.10
<br /> Total Part 3 - Services $40,813.10
<br /> Part 4 - Storm Sewer
<br />37 Salvage apron EA 1 210.00 1 $210.00
<br />38 Connect to existing storm sewer EA 1 260.00 1 $260.00
<br />39 21" RCP storm sewer, Class 3 LF 220 31.20 220 $6,864.00
<br />40 18" RCP storm sewer, Class 5 LF 147 27.80 149 $4,142.20
<br />41 15~ RCP storm sewer, Class 5 LF 524 24.40 512 $12,492.80
<br />42 12" RCP storm sewer, Class 5 LF 76 23.10 73 $1,686.30
<br />43 21" RCP flared end section, lnel trash guard EA 1 1140.00 1 $1,140.00
<br />44 12N RCP flared end section, incl trash guard EA 1 625.00 1 $625.00
<br />45 5' diameter storm CBMH EA 2 2835.00 2 $5,670.00
<br />46 5' diameter structure overdepth LF 1.2 240.00 1 $240.00
<br />47 4' diameter storm CBMH EA 6 1520.00 6 $9,120.00
<br />48 4' diameter structure overdepth LF 4.6 95.00 4 $380.00
<br />49 2' x 3' catch basin EA 2 1025.00 2 $2,050.00
<br />50 Class III random riprap CY 20 75.00 12 $900.00
<br />51 Improved pipe foundation, per 6~ increment LF 900 3.70 900 $3,330.00
<br />52 18" CMP culvert LF 30 23.10 $0.00
<br />53 12" CMP cuivert LF 20 21.00 $0.00
<br />54 18~ eMP flared end section EA 2 290.00 $0.00
<br />55 12" eMP flared end section EA 2 230.00 $0.00
<br />55 Seeding AC 0.1 2500.00 $0.00