Combined Schedule <br />Gem Lake <br />New Joint Use City Hall Project <br />all activities in this column are part of this RFP <br />RFP for Architect selection <br />Oct-06 <br />Survey Completed New Site <br />Oct-06 <br />Soils Testing <br />Oct-06 <br />Architect Selection <br />Oct-06 <br />approval to proceed <br />Oct-06 <br />Complete Schematic Design <br />Nov-06 <br />approval to proceed <br />Nov-06 <br />Complete Design Development <br />Jan-07 <br />approval to proceed <br />Jan-07 <br />Utility Connection Design <br />Jan-07 <br />approval to proceed <br />Complete Construction Documents <br />Feb-07 <br />approval to proceed <br />Feb-07 <br />Complete Utillity Design <br />Mar-07 <br />approval to proceed <br />Mar-07 <br />Bidding Process <br />Mar-07 <br />Contractor Selection <br />Mar-07 <br />approval to proceed <br />Mar-07 <br />City Utility Connections Completed Aug-07 <br />Building Completed Sep-07 <br />Move in Gem Lake City Offices Oct-07 <br />Occupancy Complete Nov-07 <br />J <br />Whjit"ear Tovnsh�p <br />White Bear Town Hall Relocation <br />activities occuring in this col- <br />umn are not part of this RFP <br />Oct-06 Survey Relocation Site <br />Oct-06 Soils Testing Relocation Site <br />Jul-07 Relocation Contractor Selection <br />Sep-07 Complete Utility Connections <br />Oct-07 Temporary move to New Building <br />Oct-07 Relocate Old Town Hall <br />Mar-08 Complete <br />Apr-08 Move <br />Apr-08 Occupancy Complete <br />11-May-108 Sesquicentennial <br />