SECTION 3 — PROJECT SCHEDULE <br />A complete project schedule identifying maior activities and actions/decisions required from the client <br />No Activity/Task Duration StartDate EndDate <br />1 Notice to Proceed 1 5.12.13 5.13.13 <br />2 Procurement/Long Lead Items 75 5.14.14 8.26.14 <br />3 Exterior Repairs & Select HVAC (May Fluctuate To Accommodate 25 6.2.14 7.4.14 <br />Program At Facility) <br />4 Exterior Painting (May Fluctuate To Accommodate Program At 5 6.9.14 6.13.14 <br />Facility) <br />5 Display Storage By Owner 14 10.28.14 11.16.14 <br />6 Demo-Lower Level 4 11.17.14 11.20.14 <br />7 Demo-Upper Level 4 11.19.14 11.24.14 <br />8 Construction-Lower Level 21 11.21.14 12.19.14 <br />9 Construction-Upper Level 21 11.25.14 12.23.14 <br />10 Interior Finishes 14 12.19.14 1.7.15 <br />11 Clean 2 1.8.15 1.9.15 <br />12 Substantial Completion 1 1.9.15 1.10.15 <br />13 Final Payment 14 1.9.15 1.23.15 <br />Contractor tasks are in 'black'; Client tasks are in "blue'; Risky activities are in "red" <br />