SECTION 3 — PROJECT SCHEDULE <br />A complete project schedule identifying maior activities and actions/decisions required from the client <br />No Activity / Task Duration Start Date End Date <br />1 Notice to Proceed 1 5/12/14 5/12/14 <br />2 Shop Drawings/Engineering 21 5/13/14 6/3/14 <br />3 Shop Drawing Approval 14 6/3/14 6/17/14 <br />4 Fabrication 49 6/17/14 8/5/14 <br />5 Installation 28 8/5/14 9/2/14 <br />6 Owner Acceptance 1 9/2/14 9/2/14 <br />7 Substantial Completion 1 9/2/14 9/2/14 <br />8 Final Payment 7 9/2/14 9/9/14 <br />Contractor tasks are in "black°, Client tasks are in "blue°, Risky activities are in "red" <br />