Laserfiche WebLink
<br />~ I ~ <br /> <br />Page 2 <br />John Shardlow <br />May 8~ 1995 <br /> <br />The following items will be required during the construction ofOwasso HiUs: <br /> <br />1. Full-time on-site inspector. <br /> <br />2. City personnel present for all tests on new lines and connections made to the City <br />system, <br /> <br />3. Minimum of 48 hours notice for all necessary tests on the newly installed sewer and <br />water lines. <br /> <br />4. City inspector will be on-site part-time. He will have the authority to modify or shut <br />down project activities if City standards are not being met. <br /> <br />S. Lot surveys are to be provided for each unit when building pennit application is <br />submitted. <br /> <br />6. The developer must install aU no-parking signage as required by t~e City. <br /> <br />7. Provide visible address numbering on each individual unit. <br /> <br />Upon the completion of the project, the following items must be submitted prior to the final <br />release of the financial surety: <br /> <br />I. Two copies of as-built drawings. One copy shaU be on single-matte drafting film. <br /> <br />2. Final payment for City Inspector time on the project. <br /> <br />3. Final inspection by the City prior to acceptance of streets and utilities. <br /> <br />If there are questions on these items or explanations are needed, please contact me at 490-2221. <br /> <br />Sincerely, <br /> <br />~c2- <br /> <br />Lon P. Aune <br />~sistant Public Works Director <br /> <br />LPA:cy <br /> <br />.. <br />