E. Schedule <br />If the City Council approves the project for construction the following is the recommended schedule <br />for this project. <br />City Council Receives Feasibility Report and Orders the Public <br />Improvement Hearing <br />January 12, 2015 <br />Conduct Public Improvement Hearing and Order Preparation of Plans <br />and Specifications <br />February 23, 2015 <br />City Council Approves Plans and Specifications and Orders Ad for Bids <br />March 2015 <br />Anticipated Bid Opening <br />April 2015 <br />City Council Accepts Bids and Awards the Construction Contract <br />April 2015 <br />Begin Construction <br />May 2015 <br />Complete Construction <br />October 2015 <br />City Council Conducts the Assessment Hearing <br />September 2016 <br />Project P -ST -SW -15-02 <br />Victoria Street Reconstruction <br />IRV <br />Feasibility Report <br />