Roseville Public Works, Environment and <br />Transportation Commission <br />Agenda Item <br />Date: April 23, 2019 <br />Item Description: Communication Items <br />Public Works Project updates: <br />• Water Booster Station Phase 2 <br />Item No: 6 <br />o The contract for this project was awarded on July 23, 2018. <br />o Work will continue through July of 2019. <br />o Work includes: HVAC upgrades, electrical upgrades including creation of an <br />electrical room, security upgrades, replacement of two pumps and replacement of <br />some underground piping and valves. <br />o Work on this phase is approximately 50% completed. <br />• 2018 Sewer CIPP <br />o This project involves lining 6.0 miles of sanitary sewer pipe and two small <br />segments of storm sewer. This project is approximately 95% complete with the <br />project scheduled to be completed by the end of the month. <br />• 2019 Sewer CIPP <br />o The 2019 project involved 4.8 miles of sanitary sewer pipe and one small segment <br />of storm sewer. The project is approximately 80% complete. All work is <br />scheduled to be completed by September. <br />• Fernwood Lift Station <br />o The City's consultant is currently designing plans and specifications for this <br />sanitary sewer lift station rehabilitation. Work on the lift station will likely begin <br />mid to late summer of 2019. <br />• 2019 Pavement Management Project <br />o This year's pavement management project consists of approximately 8.5 miles of <br />mill and overlay. The project is scheduled to begin in late spring. <br />• City Hall Parking Lot <br />o The project consists of reconstructing the parking lot between City Hall and the <br />Maintenance Facility. Work involves the realignment of the access to Civic <br />Center Drive, related storm sewer work, achieving ADA compliance, and <br />replacement of water and sewer mains under the parking lot. <br />o The project is scheduled to be awarded to Pember Companies on April 22. <br />Metropolitan Council Environmental Services updates: <br />• Avon street <br />o This project is essentially complete. The final lift of pavement will be placed this <br />spring. <br />Upper Villa <br />o This project is essentially complete. Final cleanup and restoration will occur in <br />the spring. <br />County Road 88 & Long Lake Road <br />