Laserfiche WebLink
ATTACHMENT A <br />SECTION 3 – PROJECT SCHEDULE <br />A complete project schedule identifying major activities and actions/decisions required from the client <br />No Activity / Task Duration Start Date End Date <br />1 Notice to Proceed 5/12/2022 <br />2 Shop Drawing Submitted to B32/City 5/12/20225/13/2022 <br />3 Shop Drawing Approval Returned <br />4 Padding Cover and Pole Ship Date from Impakt 84 days 5/24/20228/16/2022 <br />5 Foam Material Ship Date 56 days 6/21/20228/16/2022 <br />6 Padding System Complete and ready for shipment to project 56 days 8/16/202210/11/2022 <br />site. <br />7 Complete Padding System arrive on project Site 10/11/2022 10/13/2022 <br />8 Ice Installed <br />8 Padding System Install 3 days 10/13/2022 10/15/2022 <br />9 Substantial Completion 3 days 10/13/2022 10/15/2022 <br />10Final Payment 10/15/2022 <br /> Contractor tasks are in “black”, Client tasks are in “blue”, Risky activities are in “red” <br /> <br />